Previous Page  21 / 336 Next Page
Information
Show Menu
Previous Page 21 / 336 Next Page
Page Background

Mr. Justice Hamilton apportioned the damages as to

one third against the architect and two thirds against

the builder and Precast Ltd. He gave judgment for

£16,526 against the architect and for £33,053 against

the other defendants. He also granted a stay of

execution.

Mr. Justice Hamilton, in his judgment, said the

evidence established to the satisfaction of the court

that Mr. Lynch, in 1966, purchased the site of the old

Fever Hospital, at Midleton, with the intention of

building a guest house. It was the intention of Mr.

Lynch to apply for a grant from Bord Failte Eireann.

In accordance with their usual practices Bord Failte

appointed Mr. Robert Creedon as their consultant

architect for the purpose of considering the project

and plans and advising thereon.

In view of the defence made by the architect, the

judge said it was necessary that Court should declare

its finding of fact that Mr. Credon acted at all times

as the consultant architect for Bord Failte and that

any suggestions -made by him were made for the

purpose of informing Mr. Lynch and Mr. Beale as to

what would be required by Bord Failte to enable Mr.

Lynch to qualify for a grant. The plaintiff and Mr.

Beale were free to reject these suggestions. At no time

was Mr. Beale relieved of his obligations as the

plaintiff's architect and at no time was he controlled

by, and subject to, the directions of the consultant

architect to Bord Failte.

The Court had no doubt that it was the

intention of Mr. Lynch that the hotel would

be constructed in such a way that if necessary a second

storey could be added and that Mr. Beale so provided

in his main drawings. The Court was satisfied that it

was at all times the intention of Mr. Lynch, the

architect, and Mr. Murphy, that the roof of the

building would be a concrete one and that at no time

did they indicate otherwise to the managing director

of Precast Ltd., Mr. O'Driscoll, or any employer of

that firm.

Mr. Justice Hamilton said the evidence clearly

established that there were two major causes of the

structural defects in the building: foundation failure

with consequent serious settlement at the back or

north-east corner of the building; the failure of the

prestressed concrete beams at first-floor level which

were inadequate to carry the loads imposed on them.

The Court was satisfied that in July, 1969, the

building was in such a condition that remedial work

was so risky and dangerous that nobody would do it.

On the question of negligence the Judge said it was

clear from Mr. Beale's evidence that, because of the

fact the hotel was being built on a site on which had

stood for many years as a substantial building, he did

not carry out any investigation" of the sub-soil other

than a look at the excavations while they were being

dug by the contractor's workmen. Having regard to

the duty imposed by law on an architect, and to the

evidence of Mr. Kelliher and Mr. McCarthy, he con-

sidered that a reasonable architect, even in the

circumstances of the case and this site, would at the

very least, when the excavations were opened, have

carried out the usual probing to establish the nature

of the sub-soil. Mr. Beale was negligent in failing to

do so.

Having regard to his general duty to supervise the

construction of the building, it was the view of the

Court that he was under a duty to ensure that Messrs.

O'Reagan Precast Limited, whom he had recommended

to the builder, and whom he knew were going to

manufacture the beams, would have sufficient informa-

tion at their disposal to enable them to calculate the

load the beams would be required to carry.

The Court was also satisfied that Mr. O'Driscoll did

not seek any information about the nature of the roof

and relied on his interpretation of the plans submitted

to him and this led to his mistaken assumption that

the entire of the roof was to be of wood. The beams

were designed and manufactured by Messrs. O'Regan

Precast Ltd., and delivered to the site where they

were installed under the direction of Mr. Gerry

Callaghan, an employee of the company.

The work on the hotel progressed and was com-

pleted in November, 1967, and possession was handed

over to Mr. Lynch. At some stage prior to the

completion, and contrary to the wishes of Mr. Beale,

two 600-gallon water tanks were placed on the roof

of the hotel in the vicinity of the north-east corner.

It was alleged by the architect, and Precast Ltd., that

this contributed substantially to the trouble which

subsequently developed. The hotel was opened on

December 4th, 1967, and Mr. Lynch carried on busi-

COMPULSORY

PURCHASE

PROFESSIONAL VALUATION

and

NEGOTIATION SERVICE

Osborne King &Megran

Dublin 760251 Cork 21371

Galway 5261

also at Belfast and London

19