Previous Page  20 / 201 Next Page
Information
Show Menu
Previous Page 20 / 201 Next Page
Page Background

June 2017

ES-8

City of Morgan Hill

Water System Master Plan

redeveloped using InfoWater, a GIS-based hydraulic model also by Innovyze. The model has an

intuitive graphical interface and is directly integrated with ESRI’s ArcGIS (GIS).

ES.8

PRESSURE EVALUATION

The calibrated hydraulic model was used for evaluating the system pressures throughout the

distribution system during peak hour demand, maximum day demands, and maximum day

demands in conjunction with fire flows. Criteria for pressure and fire flows were also summarized

in the System Performance and Design Criteria chapter. Since the hydraulic model was calibrated

for extended period simulations, the analysis duration was established at 24 hours for analysis.

The hydraulic model indicates that the City’s existing distribution system performed reasonably

well during the pressure evaluation, with few exceptions noted in the Evaluation and Proposed

Improvements chapter.

ES.9

SUPPLY AND STORAGE EVALUATION

Existing and future supply requirements were identified for the City, which is required to be able to

meet the maximum day demand of the existing system with firm groundwater well capacity. Based

on the City’s existing groundwater well firm capacity, the City is capable of meeting the existing

maximum day demand; based on the anticipated future growth, the City will be required to

construct two new wells by the buildout of the General Plan.

Existing storage requirements were identified for each existing pressure zone and included the

operation, fire, and emergency storage components. The total City-wide required storage for

existing domestic water demands is calculated at 8.7 MG.

Future storage requirements were identified based on the anticipated future growth, in each

existing and future pressure zone, and will require an additional 3.3 MG of operational and

emergency storage capacity.

ES.10 CAPITAL IMPROVEMENT PROGRAM

The Capital Improvement Program costs for the projects identified in this master plan for

mitigating existing system deficiencies and for serving anticipated future growth throughout the

City are summarized on

Table ES.3

and are graphically represented on

Figure ES.3

.

The estimated construction costs include the baseline costs plus

30 percent

contingency

allowance to account for unforeseen events and unknown field conditions. Capital improvement

costs include the estimated construction costs plus

30 percent

project-related costs (engineering

design, project administration, construction management and inspection, and legal costs). The

costs in this Water System Master Plan were benchmarked using a 20-City national average

Engineering News Record (ENR) Construction Cost Index (CCI) of 10,532, reflecting a date of

January 2017. In total, the CIP includes approximately 9.8 miles of pipeline improvements, two

new wells, five new storage reservoirs, two new booster stations, a new pressure reducing valve

station, as well as other plan updates and currently planned projects, with a project cost totaling

over $48.4 million dollars.