Compressor station at Nea Messimvria

General Information

Promoter

DESFA S.A.

Operator

DESFA S.A.

Host Country

Greece

Status

Planned

Website

Publication Approval Status

Approved

Sponsors

TRA-N-971

Project

Pipeline including CS

Non-FID

Update Date

04/07/2016

Non-Advanced

Description

The project consists of the implementation of a 27 MW compressor station in order to enable flow from the Greek transmission system to TAP. This

project is the second phase of development of project "TRA-N-941-Metering and Regulating station at Nea Messimvria" .

Regulatory Decisions and

similar material conditions

Capacity Increments Variant For Modelling

Point

Operator

Year

From Gas System To Gas System Capacity

Nea Mesimvria

DESFA S.A.

2022

GR

GR/TAP

142.0 GWh/d