Benefits

Main Driver

Market Demand

Main Driver Explanation

PCI Details

PCI Benefits

Project changes the capability to transmit gas across the borders of the member states concerned by at least 10%, compared to the situation

prior to the commissioning of the project, Project concerns investment in reverse flow capacity

General Criteria Fulfilled

Yes

Specific Criteria Fulfilled

Competition, Market Integration, Security of Supply

Specific Criteria Fulfilled Comments

The project fulfills also the criteria of reverse flows, diversification of routes, N-1 regional, back-up for renewables, power-to-gas, market

integration (increase of competition), flexibility of the system and reduction of GHG emissions.

Pipelines and Compressor Stations

Pipeline Section

Pipeline Comment

Diameter (mm) Length (km) Compressor Power (MW)

Section 1

1,400

62

0

Section 2

1,200

19

0

Section 3

0

0

85

Total

81

85

Schedule

Start Date

End Date

Pre-Feasibility

Feasibility

FEED

Market Test

Permitting

Supply Contracts

FID

Construction

Commissioning

2018

2018

NDP and PCI Information

Part of NDP

Yes (Snam Rete Gas TYNDP 2016-2025)

NDP Number

TRA-F-214(into text)

Currently PCI

Yes (5.11)

CBCA Decision

No

Market Survey

Not Relevant (no CBCA decision)

Third-Party Access Regime

Considered TPA Regime

Regulated

Considered Tariff Regime

Regulated

Applied for Exemption

No

Exemption Granted

No

Exemption in entry direction

0.00%

Exemption in exit direction

0.00%

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM

Page 364 of 620

Current TYNDP : TYNDP 2017 - Annex A

Southern Corridor GRIP 2017–2026 Annex B |

189