Previous Page  14 / 44 Next Page
Information
Show Menu
Previous Page 14 / 44 Next Page
Page Background

CAPITAL EQUIPMENT NEWS

JUNE 2016

12

Johnson Crane Hire

RAISES THE BAR ON SHUTDOWN PROGRAMME

J

ohnson Crane Hire recently success-

fully completed several routine lifts as

well as a number of heavy lift projects

at a major petrochemical plant during its

annual maintenance shutdown.

This was the first time in 20 years that this

particular plant had tackled a plant upgrade

simultaneously with its annual maintenance

work.

Philip Bailey, of Johnson Crane Hire, says the

company completed the project in the 40

day contract period well within schedule and

without any LTIs being recorded.

A cornerstone of Johnson Crane Hire’s ongo-

ing success with lifting contracts is the ex-

tensive preparation work that goes into every

project, and this is done well before cranes

are deployed to site.

“We started work on the project eight months

prior to arriving on site. This involved inten-

sive studies of the lifting programme, starting

with site inspection through to undertaking

compaction tests to ensure the loading bear-

ing capacity of hard stands and marking the

positioning of all cranes on site,” says Bailey.

Johnson Crane Hire operates an extensive

fleet of cranes and was able to draw from this

fleet to ensure that those machines sent to

site were the most appropriate for the range

of lifting applications that would need to be

undertaken. The larger cranes were mobilised

a week ahead of the programme, and erected

and ready to lift a full day ahead of the lifting

schedule.

Bailey says the onerous nature of the proj-

ect, which included numerous tandem lifts in

many different areas at the same time, saw

the leading South African specialist lifting

contractor deploy a sizeable fleet of cranes

on the contract.

The maintenance aspect of the programme

used 20 smaller cranes that were deployed

at various plants on the industrial complex.

These ranged from the largest, a 120 t unit,

to the smallest, a 30 t machine.

The project component of the contract called

for eight large cranes, ranging from 180 t

units through to a 600 t crawler unit.

These large cranes working on the project

component were tasked with replacing 10

large vessels each weighing between 110 t

and 117 t. Some of these enormous pressure

vessels were 12 m in length with an outside

diameter of 12 m.

The old vessels were lifted out of the plant

using the 600 t crawler crane and Bailey says

the largest lifting radius tackled by this crane

was 42 m. The vessels were placed in the

laydown areas with the assistance of a 330 t

tailing crane.

One of the complicated heavy lifts involved

removing another important plant component,

which due to its shape and size was known

as the 'submarine'. It was cut into three 8 m

sections, each weighing 21 t. A 550 t crane

with a 21 m luffing jib was used for this lift

which called for a massive 45 metre radius.

“This entire project called for detailed plan-

ning and attention to detail in all aspects of

the work undertaken. All components had to

be carefully removed, and new units accu-

rately placed and aligned to avoid any dam-

age to the plant,” says Bailey.

Like all Johnson Crane Hire’s projects, an

impeccable safety track-record was achieved

on this site, and this is particularly noteworthy

as much of the lifting for the maintenance

work called for extensive evening shifts to

ensure the programme was met.

The lifting specialist received much praise for

its stellar performance. As Bailey notes, this is

just one of many successful lifting contracts

that the company has completed over the

years within the petrochemical sector, and

Johnson Crane Hire intends building on this

impressive track record!

b

Johnson Crane Hire operates

an extensive fleet of cranes and

was able to draw from this fleet

to ensure that those machines

sent to site were the most

appropriate for the range of

lifting applications that would

need to be undertaken.