Background Image
Table of Contents Table of Contents
Previous Page  27 / 44 Next Page
Information
Show Menu
Previous Page 27 / 44 Next Page
Page Background

wiredInUSA - August 2015

27

EUROPE NEWS

INDEX

Fugro is expanding its range of services with

the addition of a cable-lay spread onboard

the

Fugro Saltire.

The spread comprises a reel drive system

to store the cables, a tensioner to lay them,

twin winches and a quadrant deployment

system on rails.

In operation the cables are initially pulled into

the base of the wind turbine generators and

then laid along the seabed using a dynamic

positioning system to line themupaccurately

with the destination WTG. They are pulled in

using the quadrant system to manage the

cable during over-boarding and pull-in.

The initial concept for the new cable-lay

capability was developed during trenching

operations at the Humber Gateway offshore

wind farm, when E.ON asked Fugro to

investigate laying cables from the

Saltire

.

Fugro’s engineers fitted the cable-lay

equipment in six weeks, and cable-laying

was completed by February 2015.

“As well as trenching 77 array cables, we

installed eight array cables along with

second end pull-ins of cables already laid

by other contractors,” said Mike Daniel,

trenching business line manager, Fugro

Subsea Services.

Cable laying

offer

Prysmian Group has been awarded a

contract by Jersey Electricity plc for the

Channel Islands’ Normandie 1 project.

The project involves the turnkey supply

and installation of a high voltage alternate

current cable connection from France

(Surville) to Jersey. The single-length 90kV

3-core cable will stretch for 28km.

Prysmian will provide design, supply and

commissioning of the submarine and land

cable connections as part of a larger

contract awarded to the consortium

between Prysmian and VBMS. VBMS

will perform the marine cable laying

operations, including protection and

landfall activities.

The submarine cable will replace an

existing, but obsolete, Normandie 1

interconnector, and its 100MW capacity

will be shared by Jersey and Guernsey

islands under the CIEG (Channel Islands

electricity grid) partnership agreement.

The submarine cables for the Normandie 1

linkwill beproduced in theArcoFeliceplant

(Italy), the group's center of technological

and manufacturing excellence. Project

completion is scheduled for October 2016.

Normandie 1

contract