Vivergo Fuels

Ethanol Road Loading Improvements - URS

P & I Design Ltd

DOCUMENT NO: VI095002_RPT

2 Reed Street, Thornaby, UK, TS17 7AF

ISSUE: C DATE: 28.07.2016

Tel: + 44 (0) 1642 617444

PAGE 14 OF 14

Fax: + 44 (0) 1642 616447

www.pidesign.co.uk

8

DOCUMENTATION

8.1

Standardisation

It has been noted that there are multiple ways of referring to the same equipment /

systems across various documents. The opportunity should be taken to standardise

terminology and acronyms across documentation where they refer to the same item.

To aid this process it is suggested the abbreviations and definitions section of this

document act as a reference point and be expanded as necessary.

9

TESTING

The existing system is to remain operational throughout the changeover, with a phased

changeover being implemented to permit continued operation. An overall testing plan

will be developed to define and control the overall testing programme.

The nature of the system with its component building blocks means that standalone

testing will be performed on various systems prior to joining together in an integrated

test. Interfaces between the various systems will require particular attention.

Vivergo propose to setup a virtual test network. Further details and diagrams will be

supplied in due course.