Ten-Year Network Development Plan 2017 Annex C: Demand and Supply, C 1: Country Specifics
RO (ROMANIA)
Final gas demand
The TSO submitted the inputs for the different scenarios. No further comments have
been reported.
Power generation – general methodology
The TSO submitted the inputs for the general methodology. No further comments
have been reported.
RS (SERBIA)
Final gas demand
No Serbian data was submitted during the data collection. The total Serbian demand
for the TYNDP 2017 was calculated based on the available information about gas
exports to Serbia during the years 2014 and 2015 in the ENTSOG Transparency
Platform. For all scenarios the average yearly demand is the average export, the fig-
ures for the 2-week case are the maximum observed during 14 consecutive days
and the Peak is the daily maximum. The figures representing the total demand are
categorized as final demand.
Power generation – general methodology
See above.
SE (SWEDEN)
Final gas demand
The TSO submitted the inputs for the different scenarios. No further comments have
been reported.
Power generation – general methodology
The TSO has submitted its own data for the scenarios.
SI (SLOVENIA)
Production Data
At the moment in Slovenia there is no natural gas production facility in operation de-
livering gas to the transmission system. Based on the existing status of investments
and considering estimated capacities and possible economical aspects of operation
of natural gas production facilities, so far for the TSO, it is not possible to prepare a
reliable estimation of yearly produced quantities. The prediction of yearly quantities
will be possible based on the development of the first Slovenian project in the field
of natural gas production.