130
Engineering Fee Description
Current Fee
Adopted Fee Change
Floodplain Development Permit
Elevation Certificate
$150
Map Revision (CLOMR/LOMR)
$1,000
Riparian Buffer Development (No
practical alternatives) Submittal
2 Reviews
$250
3
rd
Review and thereafter
$75
Stormwater Plan Review Fee (Includes 3
review or if submitted concurrent with
Site Plan includes first 4 reviews.)
$550 + $55/acre per disturbed acre
Re-Submittal Stormwater Plan Review
Fee (4th submittal and each thereafter.)
$350
Project Close-Out Fees (Paid upon
Project Completion)
Record Drawing Review - Includes 2
Reviews Note: Morrisville Only, See
Town of Cary for fees related to utility
As-Builts
$250
Re-submittal Record Drawing - 3rd
Review and each Thereafter
$150
Stormwater As-Builts - includes 2
reviews
$250 per
BMP
SCM
Stormwater As-Builts - 3rd Review and
each Thereafter
$125
Miscellaneous Fees
Administrative Appeal (EDCM)
$610
Alternative Standard (EDCM) - Request
for alternative standard
$150 per request standard
Bulletin Drawing Review
- per review
(includes 2 reviews)
$150
Interpretation (EDCM)
$205
Retaining Wall/Other Structures
Submittal
1st Review
$150