Capital Improvements Program FY 2015 - 2024 - page 165

City of Greensboro
RESULT AREA
DEPARTMENT
285
2015-2024
Capital Improvements Program
Tracking#
PROGRAM
State/Federal Grant Program
DISTRICT
Var
ACCOUNT NUMBER
441-6004-01
PROJECT TITLE
US 220 Sidewalk R-2309AB
TYPE
REQUEST
New
PROJECTED
START
PROJECTED
COMPLETION
Spring 2012
Winter 2016
Infrastructure
Transportation
PROJECT DESCRIPTION
This project made possible by the action of the MPO Transportation Advisory
Committee, working in cooperation with NCDOT, to direct Federal Surface
Transportation Program Direct Apportionment (STP DA) funds to the city for this
project. The project involves construction of sidewalk along US 220
(Battleground Avenue) from Horse Pen Creek Road to Owls Roost Road as part
of NCDOT’s TIP Project R-2309 AB.
$192,520
$192,520
Approved Funding:
Estimated Budget:
BUDGET INFORMATION
BUDGET COMMENTS
Expenses
Planning/Design
Fiscal Year
Land
Construction
Equipment
Fiscal Year Total
0
0
0
0
0
14 15
-
0
0
0
192,520
192,520
15 16
-
0
0
0
0
0
16 17
-
0
0
0
0
0
17 18
-
0
0
0
0
0
18 19
-
0
0
0
0
0
19 24
-
192,520
0
0
0
192,520
Total
Revenue
General
Fund
Enterprise
Fund
Grants
Authorized
Bonds
Unauthorized
Bonds
Unauthorized
Bonds 2
Revenue
Bonds
Fiscal
Year
Other
Revenue
Fiscal Year
Total
0
0
0
0
0
0
0
0
0
14 15
-
192,520
0
0
0
38,504
0
0
0
154,016
15 16
-
0
0
0
0
0
0
0
0
0
16 17
-
0
0
0
0
0
0
0
0
0
17 18
-
0
0
0
0
0
0
0
0
0
18 19
-
0
0
0
0
0
0
0
0
0
19 24
-
0
0
38,504
154,016
0
0
Total
0
192,520
0
Operating Impact
Fiscal Year Total
Fiscal Year
Personnel
Maintenance
Operations
Capital Outlay
Revenues
0
0
0
0
0
-
14 15
0
0
0
0
0
-
15 16
0
0
0
0
0
-
16 17
0
0
0
0
0
-
17 18
0
0
0
0
0
-
18 19
0
0
0
0
0
-
19 24
Total
0
0
0
0
0
153