Peter – please see attached pictures for the last truss on the south end by HH. Please advise how you want the control joints at the top and bottom to finish into the gyp wall since it is only half a truss. Zack Trause Project Engineer

SKANSKA WALSH Design-Build Joint Venture LaGuardia Airport CTB Replacement Project Hangar 5A Runway Drive Flushing, NY 11371 Mobile: (917) 565-6140 Think twice before you press "print."

This message, including any attachments hereto, may contain privileged or confidential information and is sent solely for the attention and use of the intended addressee(s). If you are not an intended addressee, you may neither use this message nor copy nor deliver it to anyone. In such case, you should immediately destroy this message and kindly notify the sender by reply email. Thank you.