EXHIBIT “D” Attachment to Agreement No. 1213126J-000.620027, dated July 16, 2018 , by and between SPEARHEAD CONSTRUCTION LLC and Skanska Walsh Design-Build JV for Furnish and Install Building Framing and Partitions for Pedestrian Bridge B at LaGuardia Airport Central Terminal Building Replacement Project, New York, LaGuardia Airport Queens, New York .
Install MEP Systems Overhead
May 2019
August 2019
Install Gypsum Board Assemblies all of Level 4 and Public Areas
September 2019 September 2019 October 2019 October 2019 November 2019 December 2019 November 2019 November 2019
November 2019 September 2019 October 2019 October 2019 November 2019 December 2019 December 2019 December 2019
Install Metal Stud Framing and Ceiling Sheetrock etc
Install Doors & Hardware
Install GFRC at Radiator Enclosure
Install Carpeting
Install Interior Handrails
Painting
Systems Commissioning
White Glove Cleaning of Bridge
Dec 15, 2019 Jan 1, 2020
Dec 31, 2019
Open To Public
** Double Shifts as required to complete all framing, gypsum board assemblies, GFRG and GFRC, door and hardware, and install accessories and maintain the Project Schedule.
2.
SCHEDULE TARGETS
The following is a list of schedule dates for Subcontractor’s Project Work:
3. REQUIRED LEAD TIME AFTER SUBMITTAL APPROVAL*
Item Description
Lead Time
GFRC GFRG
14 Weeks 14 Weeks
1. 2. 3. 4. 5. 6. 1. 2. 3. 4. 5. 6.
Weeks Weeks Weeks Weeks
List other items over four (4) weeks
Lead Time
Weeks Weeks Weeks Weeks Weeks Weeks
*Subcontractor to complete form
4. ANTICIPATED DURATIONS FOR KEY SUBCONTRACTOR ACTIVITIES*
Exhibit D, Page 2 of 3
Project Schedule/Milestones
Version 4.0
(02/22/2017 ed. Rev. 0)