Steam Generator & Fluid Heater Installation Manual

IMPORTANT KEEP CLAYTON EQUIPMENT CLEAR OF ALL OBSTRUCTIONS. DO NOT ROUTE ANY NON-CLAYTON PIPING, ELECTRICAL CONDUIT, WIRING, OR APPARATUS INTO, THROUGH, OR UNDER CLAYTON EQUIPMENT. ANY OBSTRUCTIONS CREATED BY SUCH NON-CLAYTON APPARATUS WILL VERY LIKELY INTER- FERE WITH THE PROPER OPERATION AND SERVICING OF THE EQUIPMENT. ALL SUCH INTERFERENCE IS THE SOLE RESPOSIBILITY OF THE CUSTOMER. CLAYTON’S PLAN INSTALLATION DRAWINGS, INCLUDING JOB-SPECIFIC DRAWINGS, ARE FOR VISUAL REFERENCE ONLY.

2.2 Positioning and Anchoring Equipment 2.2.1 General Installation Requirements

Lifting instructions are provided in Appendix A. Proper rigging practices and equipment must be applied when lifting this equipment. Forklifts with roll bars can be used for installations with overhead space limitations.

WARNING DO NOT attach rigging gear to the top coil lifting hook or any part of this equipment other than the main frame.

When used, mounting legs with fasteners are provided. All legs and fasteners must be attached. DO NOT alter the lengths of the mounting legs without first consulting Clayton. The mounting legs are designed to provide adequate space and accessibility for servicing the equipment. Proper floor drains must be provided under the generator(s). MAKE SURE ALL EQUIPMENT IS LEVELED AND ALL ANCHORING POINTS ARE USED. Level the equipment using full-size, stainless steel, slotted shims that match the equipment pads designed and provided on the equipment. Clayton recommends full-size slotted shims. If slotted machine shims are used, Clayton requires C-size or larger for pump skids and E-size for generator and water skids. Use full-sized anchors to anchor the equipment. Make sure anchors are strong enough to withstand operating, wind, and seismic loads that exists in the installation location. To enhance serviceability and accommodate service personnel, Clayton recommends placing its gen- erators, main positive displacement (PD) feedwater pumps, feedwater skids, and water treatment skids on 4– 6 inch (10–15 cm) high equipment maintenance pads. These equipment maintenance pads on which the equipment will be installed must be 3–6 inches (8–15 cm) wider and longer than the equipment base plates. Make sure the equipment maintenance pads are properly reinforced and leveled. Fully grout into place all generators, pumps, and skids, after leveling and anchoring, to provide ade- quate support and minimize equipment vibration. Grouting is important, but it does not replace the use of metal shims under each anchor bolt location. Every anchor hole location on the equipment skid(s) requires an anchor bolt.