REA Final - 22 Dec 20 - eBook - 1682 pages
CHANGE ORDER LaGuardia Pedestrian Bridge B
Date:
December 31, 2019
To: Skanska Walsh Jv Attention: Frank Corallo
Contact: Sean Reed
Spearhead Construction
Address: Hangar 5A Runway Drive Flushing, NY 11371 Email: Frank.Corallo@SkanskaWalsh.com
Email: Sean@SpearheadCx.com
Office: (718) 310 ‐ 4615
Office: 631.793.7422
Spearhead Change Order No.
7
Scope Affected: Escalator East and South Walls
Description Install new frame walls in lieu of poured concrete walls.
Reason
Directed by SWJV.
Justification and Support As shown on A47 ‐ 60 (attached) and A40 ‐ 55 (attached). Initial installation of the walls (from inside) performed on 10/22/19. Walls were closed up from the exterior on 11/17/19 and 11/24/19.
Projected Scope Workdays: Change Order Added Workdays:
Current Contract Price:
Change Order Price:
0.5
$7,420.95
Net Order Price:
Net Workdays:
(Itemized Work Breakdown Follows)