The UK Offshore Oil and Gas Fabricators Directory 2014

Projects and Markets (continued)

Buzzard Platform Client:

Nexen Petroleum UK Ltd

Contract:

Fabrication Contract (topside and bridges)

Completion Date: 2010 Structure:

Production sweetening topsides and bridge (Heerema Hartlepool)

Weight Topside:

6,000 tonnes

Bridge: 500 tonnes Size (Length x Width x Height) Topside:

60 x 36 x 42 metres

Bridge:

50 metres

Sheringham Shoal Substation Topsides Client: AREVA T&D Ltd Contract:

Engineering, procurement and construction (EPC)

Completion Date: 2010 Structure:

Two offshore wind substation topsides

Weight Topsides:

806 tonnes and 803 tonnes

Size (Length x Width x Height) Topside:

30.5 x 17.7 x 16 metres

>

page 64

THE UK OFFSHORE OIL AND GAS FABRICATORS DIRECTORY 2014

Made with FlippingBook - professional solution for displaying marketing and sales documents online