Background Image
Previous Page  24-25 / 66 Next Page
Basic version Information
Show Menu
Previous Page 24-25 / 66 Next Page
Page Background

wiredInUSA - May 2012

wiredInUSA - May 2012

EUROPE

NEWS

EUROPE NEWS

Cable supplier Nexans has been

awarded the contract to supply a total

of 57km of high voltage subsea power

export cables to Northwind NV in the

North Sea. The project comprises 14km

of cable to connect Belwind Phase 2

to the Northwind wind farm, together

with a further 43km of cable to transfer

a total of 381MW produced by both

wind farms to the onshore grid

connection at Zeebrugge.

In addition to the design, type testing

and supply of the XLPE subsea cables,

Nexans will also supply the onshore

transition joints to connect the subsea

cables to the land cables, the accessories

for the two platforms, comprising

hang-off and GIS (gas insulated

switchgear) terminations, and four

repair joints.

The Northwind wind farm will comprise

72 wind turbines, to deliver 216MW

installed capacity to the Belgian

electricity network.

The 14km section of 245kV cable

connecting Belwind Phase 2 to

Northwind will consist of three copper

cores, each with a cross section of

400mm

2

. The majority of the 43km,

245kV connection from Northwind

to Zeebrugge will comprise of three

1,000mm

2

copper cores.

For a length of the cable route

the cable will be buried 9 meters

below the seabed for protection from

dredging activity. To maintain the

electrical performance of the cable

along this channel, the copper cross

section will be increased to 1,200mm

2

on a 4km section. This section of cable

will have an outer diameter of 265mm

and will weigh 130kg per meter.

Offshore

cabling

contract

Picture : www.bigstockphoto.com ‘Spring’ Photographer - ‘ Rafal Steciuk’

25

INDEX

24