Table 8.1  Unit Costs

   Sewer System Master Plan

   City of Morgan Hill

PRELIMINARY

Pipe 

Size

New/Parallel/Replacement

CIPP

Cleaning

CCTV

(in)

($/unit length)

($/unit length) ($/unit length)

($/unit length)

6

156

24

1.03

1.29

8

171

37

1.03

1.29

10

185

51

1.03

1.29

12

199

64

1.03

1.29

15

270

84

1.03

1.29

Pipelines

Improvement Type Unit Cost

18

313

105

1.03

1.29

21

370

125

1.03

1.29

24

426

145

1.03

1.29

27

498

‐‐

‐‐

1.29

30

569

185

‐‐

1.29

36

711

‐‐

‐‐

1.29

22$ per inch diameter per linear foot

Notes :

2/17/2017

1.   Unit costs are based on an ENR CCI Index Value of 10,532 (01/2017)

Pipeline Casings