Table 8.1 Unit Costs
Sewer System Master Plan
City of Morgan Hill
PRELIMINARY
Pipe
Size
New/Parallel/Replacement
CIPP
Cleaning
CCTV
(in)
($/unit length)
($/unit length) ($/unit length)
($/unit length)
6
156
24
1.03
1.29
8
171
37
1.03
1.29
10
185
51
1.03
1.29
12
199
64
1.03
1.29
15
270
84
1.03
1.29
Pipelines
Improvement Type Unit Cost
18
313
105
1.03
1.29
21
370
125
1.03
1.29
24
426
145
1.03
1.29
27
498
‐‐
‐‐
1.29
30
569
185
‐‐
1.29
36
711
‐‐
‐‐
1.29
22$ per inch diameter per linear foot
Notes :
2/17/2017
1. Unit costs are based on an ENR CCI Index Value of 10,532 (01/2017)
Pipeline Casings