Previous Page  37 / 64 Next Page
Information
Show Menu
Previous Page 37 / 64 Next Page
Page Background

November 2015

MODERN MINING

35

PLATINUM

D

esign of the No 2 Shaft headframe

for the first phase of Ivanplats’

Mokopane project commenced

in 2014. The project, designed

to produce 433 000 PGM ounces

per annum, will ultimately be a 12 Mt/a opera-

tion. Ivanplats is a wholly-owned subsidiary

of Ivanhoe Mines.

The design of the No 2 Shaft headframe

was awarded in June 2014 to shaft-sinking

expert Murray & Roberts Cementation. It will

be the main production shaft, capable of hoist-

ing 6 Mt/a of ore, and will also transport large

mechanised equipment between surface and

underground.

By comparison with most steel-frame PGM

headgears in South Africa, it will be a consider-

able concrete structure – 100,5 m in height. The

lined shaft will be 10 m in diameter. The head-

frame will house all equipment necessary for

sinking and operating the shaft thereby reduc-

ing the surface footprint.

The No 2 shaft will be sunk to a depth of

1 080 m and will accommodate two “high mass,

high speed” 40-t skips running at 18 m/s, Genis

says. It will also be capable of conveying 225

persons in a single deck using a cage and coun-

ter weight arrangement.

“This milestone achievement can largely

be attributed to our Platreef project team, who

dedicated themselves to delivering a functional

quality design,” says Genis.

Ivanplats expects to start early works for

the No 2 shaft this year, including the boxcut

and hitch foundation civil works. The boxcut

designs are complete and the contract for the

early engineering works for the winding equip-

ment has been awarded to South Africa-based

FLSmidth.

The tall headframe will be located in close

proximity to a number of communities, Genis

notes. “As a result, we have incorporated unob-

trusive lighting and have also implemented

Design of

high-tonnage

headframe

completed

design initiatives to reduce noise and dust lev-

els. The overall aesthetic look also had to be

considered and subsequently we have designed

a simple headframe with fluted features using

concrete throughout.”

The “limited real estate” necessitated that

the two tower-mounted Koepe winding sys-

tems be positioned about 82 m above ground.

Additionally, a single drum auxiliary winder is

mounted at a lower elevation in the headframe.

“Working at these heights with heavy con-

crete and steel loads presents significant

constructability challenges,” principal engi-

neer Charles Bethel admits. To compensate

for potential obstacles in this regard, Murray

& Roberts Cementation established close ties

with its infrastructure sister company and

spent a significant portion of its time review-

ing handling equipment and crane lifting

arrangements.

Time was allocated to power supply, cabling

and piping layouts to ensure circuits which

will be easy to install and maintain. Chiller

plants located on the headframe roof will form

a HVAC (heating, ventilating and air condition-

ing) system to cool the winding equipment and

pressurise the upper three levels.

“Our headframe design provides Ivanplats

with pre-sinking flexibility from either the col-

lar or lower level, enabling a fast transition

into actual shaft sinking,” says Jan Vermaak,

Murray & Roberts Cementation mine engineer-

ing manager.

A purpose-designed sinking headgear is not

required for the initial sinking phases. “We

have incorporated start-up sinking arrange-

ments into the main headframe. By mass,

approximately 93 % of the steel required for

the headframe will be permanent at the start

of sinking, meaning the changeover from sink-

ing to permanent will be minimised,” says

Bethel. This equates to cost and time savings

for the project.

Murray & Roberts Cementa-

tion has recently completed

the design of Ivanplats’

mechanised, high tonnage

Platreef No 2 shaft head-

frame.

Murray & Roberts Cementation has demonstrated its high quality

design and drawing capabilities having recently completed the design

of Ivanplats’ mechanised, high tonnage Platreef No 2 shaft headframe.

The design of a headframe of this magnitude is a first for the company

and marks a huge milestone achievement, says Theo Genis, Murray &

Roberts Cementation study manager.

“Working at

these heights

with heavy

concrete and steel

loads presents

significant

constructability

challenges.”