CONSTRUCTION WORLD
JULY
2017
38
WATER ENGINEERING
Water use licences are required by a range of water users from mines
and industry to property developers and farmers; even public sector
organisations like local authorities, provincial authorities and road
agencies may need authorisation for projects.
According to Manda Hinsch, partner and principal water and
environmental scientists at SRK Consulting, the new regulations
are a positive step that aligns the timelines for Water Use
Licence Authorisations (WULAs) with those already applying
for environmental authorisations as required by the National
Environmental Management Act (NEMA).
“Both processes now promise authorisations within 300 calendar
days, if all documents and studies are in order,” said Hinsch. “In the
past, receiving water use authorisation could take up to three to five
years.” She said these delays often led to applicants simply starting
project construction without the necessary authorisation, since
the positive socio-economic impact of proceeding was deemed to
outweigh the negative environmental impacts.
“Also, assessment processes within the department were not
always well-monitored, so it was difficult to track the stage which an
application had reached within the process,” she said.
Hinsch said the process will now begin with a pre-application
meeting with the water authority, followed by the submission of the
application within five days. A date for a site visit then needs to be
finalised within five days after that, and the visit itself must take
place within 30 days.
The authority is then expected to respond within five days
of the site visit, outlining the exact requirements for the WULA.
The applicant then has 105 days to prepare and submit the
necessary technical reports, as well as conduct the public
participation processes.
Following submission, the authority has 10 days to acknowledge
receipt of the application, and 139 days to consider the documenta-
tion and make a decision – after which it has five days to actually
issue the decision.
“The new regulations also formalise the public participation
requirements, which were neglected in the past – particularly
if a WULA was required without the need for an environmental
authorisation,” said Hinsch.
“These regulated timelines are tight, and place pressure on both
the department and applicants to work quickly and efficiently,”
she said, adding that SRK also makes use of in-house specialists
to undertake the
hydrological and
geo-hydrological
studies, often required
for WULAs, further
simplifying and
speeding up
the process.
The aim of the dialogue was to provide input into the conceptual-
isation of the country’s new master plan on water and sanitation.
This plan is expected to be finalised as early as the end of the year.
Speaking at the dialogue, Deputy Minister of Water and Sanitation,
Pamela Tshwete, challenged stakeholders in particular big
business, to assist with the development and implementation of
the master plan.
In response, Eskom’s water management lead, Nandha Govender,
presented private sector initiatives the public utility is implementing
together with corporate partners, the Department of Water and
Sanitation and civil society through the Strategic Water Partners
Network (SWPN). SWPN is a multi-stakeholder partnership aimed
at helping close South Africa’s 17% demand-supply water deficit
gap, by 2030. For example, the partnership has worked to address
some of the water resource management challenges affecting South
Africa’s mining industry.
Although mining companies currently treat their effluent in
accordance with national regulations, the continued installation
of energy and capital intensive mine water treatment facilities
is unlikely sustainable in the long run. While a relevant regional
approach for an entire mining area is ideal, it requires agreement on
actionable solutions, as well as how costs are partitioned among
mining companies – with respect to operational mines, and the
state – with respect to non-operational mines as required by law.
To address this challenge, the SWPN helped establish a mine
water coordinating body in the Emalahleni (formerly Witbank) coal
mining area, which begins approximately 100 km east of the capital
city, Pretoria and runs mostly along the Olifants River catchment.
The mine water coordinating body brings together area stakeholders
from the public and private sectors and civil society to address
some of the mine’s most pressing challenges.
Over the next 30 years, several mines are expected to close
in the Emalahleni region. At present, area stakeholders must
determine who will manage, operate, maintain and finance post
closure discharge water treatment facilities, already built by mining
companies. Given that costs will not be recovered by selling treated
water to municipalities alone, even when initial capital costs are
subtracted, another solution must be found.
Water and sanitation strategy
Recently, South Africa held its first National Water a
nd
Sanitation Dialogue. It gathered stakeholders from
the agriculture, manufacturing, energy and mining
sectors amongst others.
AECOM recently worked on the Eastern Basin Acid Mine Drainage (AMD)
treatment plant. Acid mine drainage is generated when ore and other
sulphide-containing mining waste is exposed to oxygen and water.
Curbing delays in licencing
Recent regulations from the Department of Water and
Sanitation (DWS) will hopefully overcome the long
delays in securing water use licences, and allow more
streamlined implementation of projects.
Manda Hinsch, partner
and principal water
and environmental
scientists at
SRK Consulting.




