Previous Page  66 / 88 Next Page
Information
Show Menu
Previous Page 66 / 88 Next Page
Page Background

66

A U G U S T , 2 0 1 6

&

What is the biggest

construction nightmare you

have uncovered while doing

a project, and how was it

handled?

"I find the most frustrating of transition problems to be

water penetration issues. My first experience took place

nearly 20 years ago, with an association with a significant

number of unit basements with substantial leaks. We went

about the process in the usual way, with the association

engineer inspecting, diagnosing the problem, and offer-

ing a solution. After some back and forth, the developer

agreed to the specified fix, and executed it. The problem

was that the agreed upon solution did not fix the problem,

and the leaks continued, but now were the Association’s

problem, rather than that of the developer, because the

developer had been released by doing what the associ-

ation expert told them to. The lesson that I learned is that

water problems should be viewed as a collaborative prob-

lem, and releases given only when the solution is found to

work, in the real world, and not just on paper."

Michael Pesce, PCAM

Associa

®

– Community Management Corp.

"The worst construction nightmare I uncovered was during

a repaving project. As the contractor began to mill, we

discovered the builder had buried broken / unused doors

and windows under the road. The additional subsurface

excavation, restoration & disposal cost several thousands of

dollars. This occurred just 3 years after transition had been

completed."

Dan Fusco, CMCA

Associa

®

– Community Management Corp.

"Halfway through a full lobby renovation, the specialized

tile intended for the floors, previously confirmed as shipped,

was backordered by a full 6 months. It had taken the

Association so long to choose the design based on that

product, but there was no was that the project could sit

that long. We held an emergency meeting at which our

vendor offered a presentation with available alternatives.

The community responded enthusiastically and positively –

we were able to achieve a solid vote on a different option,

and continued the renovation with a delay of only 2 days."

Alexandra Crossett

Associa

®

– Community Management Corp.

"A few years back two families in a townhome building

suddenly experienced un-level counter tops, sloping floors

and cracked tiles. The issues were serious enough to hire

an engineer to do some invasive testing then.

Based on the reports received, experts proposed remov-

ing the existing foundations and properly back filling and

stabilizing the soil before re-pouring the foundations. The

estimated timetable of displacement was a few months. The

families were moved to extended stay hotels. Furniture,

flooring, appliances and all personal possessions on the

first levels were removed to pods and storage facilities.

Well, during foundation removal the contractor found the

concrete to be several inches thicker than normal, an indica-

tion the developer likely knew there was a drainage issue or

high water table. In addition, soil had “disappeared” a foot or

two below the footings. There was no sign of water or wash

out so where the soil went remains a mystery.

With no guarantee the proposed stabilization and back

filling would not eventually result in “disappearing soil”, the

engineers went back to the drawing board and specified

helical piles be installed into the bedrock to shore up the

sinking foundations.

These piles are hydraulically screwed into the ground and

attached to an elaborate anchoring system. Some piles were

driven more than 15 feet down before solid bedrock was hit.

The final timetable when all was said and done – 7 months!"

Terry Viggiano, CMCA, AMS, PCAM, ARM,

Whispering Woods, RCP Managment