City of Morgan Hill

2015 Urban Water Management Plan

2015

City of Morgan Hill

10.0

CHAPTER 10 – PLAN ADOPTION, SUBMITTAL AND

IMPLEMENTATION

This section includes the process undertaken for adoption and submittal of the UWMP as well as

the plan required to implement the UWMP. Ways in which the public can access the UWMP is

also described in this section.

10.1 INCLUSION OF ALL 2015 DATA

The City is preparing the 2015 UWMP on the basis of a calendar year and preparation of the plan

was completed following the end of calendar year 2015. Relevant data has been updated through

December of 2015.

10.2 NOTICE OF PUBLIC HEARING

This section documents the public notification process and when notice was given.

10.2.1 Notice to Cities and Counties

Law

The City provided notice to relevant stakeholders, summarized in

Table 10-1

, on March 28, 2016;

this notification date was more than the required 60 days prior to the public hearing on the 2015

UWMP.

10621 (b) Every urban water supplier required to prepare a plan shall…at least 60 days prior to the

public hearing on the plan…notify any city or county within which the supplier provides

water supplies that the urban water supplier will be reviewing the plan and considering

amendments or changes to the plan.

10642 …The urban water supplier shall provide notice of the time and place of hearing to any city or

county within which the supplier provides water supplies. A privately owned water supplier

shall provide an equivalent notice within its service area…