CHAPTER 10 – PLAN ADOPTION, SUBMITTAL AND
IMPLEMENTATION
This section includes the process undertaken for adoption and submittal of the UWMP as well as
the plan required to implement the UWMP. Ways in which the public can access the UWMP is
also described in this section.
10.1 INCLUSION OF ALL 2015 DATA
The City is preparing the 2015 UWMP on the basis of a calendar year and preparation of the plan
was completed following the end of calendar year 2015. Relevant data has been updated through
December of 2015.
10.2 NOTICE OF PUBLIC HEARING
This section documents the public notification process and when notice was given.
10.2.1 Notice to Cities and Counties
Law
The City provided notice to relevant stakeholders, summarized in
Table 10-1
, on March 28, 2016;
this notification date was more than the required 60 days prior to the public hearing on the 2015
UWMP.
10621 (b) Every urban water supplier required to prepare a plan shall…at least 60 days prior to the
public hearing on the plan…notify any city or county within which the supplier provides
water supplies that the urban water supplier will be reviewing the plan and considering
amendments or changes to the plan.
10642 …The urban water supplier shall provide notice of the time and place of hearing to any city or
county within which the supplier provides water supplies. A privately owned water supplier