Previous Page  37 / 44 Next Page
Information
Show Menu
Previous Page 37 / 44 Next Page
Page Background

Mechanical Technology — April 2016

35

Innovative engineering

Above:

The vertical shaft mucker (VSM): The

use of VSM systems with clamshell muckers

at Venetia is a South African first.

Left:

A view of the Venetia headgears for the

production and service shafts.

Right:

The vertical drill rig (VDR): Murray

& Roberts Cementation has incorporated

mechanised drilling systems underneath the

pre-sink stage.

SA’s shaft sinking specialist

loading system significantly reduces risk

as well as tipping cycle times.

Since Murray & Roberts Cementation’s

pre-sink gantry is rail mounted, on com-

pletion of the first pre-sink operation at

Venetia, it was possible to transport the

entire system on temporary rails to the

position of the second shaft. “For Venetia

we drove the whole set-up, including the

stage and the portal cranes, across to

the new pre-sink site at the mine. The

set up stage for the second pre-sink was

completed inside of five days, a process

that used to take us up to a month,” Du

Plessis reveals.

Turning attention to innovations on

the pre-sink stage itself, the company

has also significantly improved the safety

and effort required for drilling. “We

have incorporated mechanised drilling

systems underneath the pre-sink stage.

The system consists of six vertical drill

rigs supported on swivel arms suspended

underneath the stage. Each operator

guides the drill and manoeuvres it to

match the pattern of holes required for

the blast. An inline pneumatic air leg on

the rock drill extends to create thrust on

the rock drill between the stage and the

floor and, after drilling, for drill retraction.

Much less physical effort is involved and

the operator simply guides the drill’s posi-

tion – and there are no longer any manual

drill operations on the shaft bottom,” Du

Plessis explains.

Also simplified is the shaft lining

process: “Previously, we had to handle

the shuttering and formwork from rigger

mounts drilled into the shaft lining. But

we have now developed proprietary shut-

tering, suspended from the sinking stage.

The shutter depth is 6.0 m, thus after

each 6.0 m of excavation, the shutter

is positioned 12-18 m above the shaft

bottom – and this shutter can be left in

place during drilling and blasting opera-

tions,” says Du Plessis.

The shuttering is suspended from

the lining above using suspension rods,

which remain embedded in the concrete

lining after pouring and protrude through

the shutter at the bottom. To seal the

bottom end of the shutter, scribing sup-

port bars are pushed out towards the

sidewalls, curved scribing planks are laid

and fine steel mesh is used to seal to the

rock interface. A series of steady brackets

between the formwork and rock holds

the shutter securely in place to contain

the self-levelling concrete while it sets.

Air hoist are used to hold the top sec-

tion of the shutter in position in prepara-

tion for concrete pouring. The concrete

is then poured into the shuttering using

concrete kettles, or kibbles, to supply the

concrete from surface. Once the concrete

has settled, the shuttering is ready to

be moved to the next position. The key