Background Image
Previous Page  61 / 82 Next Page
Information
Show Menu
Previous Page 61 / 82 Next Page
Page Background

January 2015

MODERN MINING

59

DIAMONDS

Top projects

Left:

Plant and infrastruc-

ture layout post 15 years of

phase 1 mining.

Below:

Layout of the new

plant, which will have a

capacity of 3,6 Mt/a.

grade – approximately 2 to 6 cpht. This low

grade is offset, at least in the case of Letšeng, by

the consistency with which large high-quality

stones are produced – in fact, Letšeng typically

gets an average of well over US$2 000/carat for

its diamonds.

“Liqhobong, by contrast, has an exception-

ally high grade by Lesotho standards of 33 cpht

but its diamonds have generally been regarded

as low value,” he explains. “The base case price

per carat used in the revised DFS is a relatively

modest US$107 and the project, of course, is

highly viable on this basis. We do believe, how-

ever, that Liqhobong – like its neighbours – has

the ability to produce large stones. The figure

of US$107 is based on the recovery and sale

of the diamonds from the pilot plant operation

but does not take into account breakage of large

stones in the plant which – due to shortfalls in

its design – was a persistent problem.

“We estimate that over the 22 months we

operated the pilot plant nine large 100 carat

plus stones were crushed. Based on an analysis

of the fragments, three of them were calculated

to be over 200 carats, with the biggest being

an approximately 430 carat yellow diamond.

Taking large stones into account, our expec-

tation is that the average price could rise to

US$156 per carat – hence the upside case in

the revised DFS.”

The DFS envisages open-pit mining of the

main pipe down to 393 m over 15 years –

exploiting a reserve of over 11 million carats at

a grade of 32,07 cpht – at an average strip ratio

of waste to ore of 2,28. The ore will be treated in

the Main Treatment Plant (MTP) which utilises

a conventional flowsheet comprising scrub-

bing, screening, crushing, concentration via

DMS, and final recovery using X-ray machines.

The plant will have 2 x 250 t/h streams. The

mining cost is estimated at R21,5/t and the pro-

cessing cost at R57,8/t. The total cost per tonne

of ore processed is projected at R140,92/t. The

mine will have a power draw of approximately

5 MW, to be supplied from the Lesotho grid.

With the funding under its belt and avail-

able in the second quarter of 2014, Firestone

was able to award the key contracts and

launch the construction phase of the project

in May/June 2014 and by 20 June over R1 bil-

lion of the project budget had been committed.

DRA was appointed as the EPCM contractor

while other awards include the residue storage

facility or RSF (Turnkey Civils Lesotho), the

civils and earthworks (Stefanutti Stocks), the

structural, mechanical, piping and platework

or SMPP (SMEI Projects) and the overhead

power line required to connect the site to the

Lesotho grid (Infrastructure Projects). Some of

these elements are substantial with the RSF

contract being worth R330 million, the civil

and earthworks R263 million and the SMPP

R327 million.

In addition, the contracts for the supply of

long-lead items such as the crushers, scrubbers,

apron feeder, vibrating screens and primary

rock breaker have all been placed. The fact that

the mining industry globally is in a subdued

state has assisted Firestone inasmuch as suppli-

ers generally have capacity and have submitted

competitive prices. The escalation risk has

“We estimate

that over the

22 months we

operated the

pilot plant nine

large 100 carat

plus stones were

crushed.”

Stuart Brown, CEO,

Firestone Diamonds