SUPERLIFT 3800 CRAWLER CRANE

installs steel bridge

B

efore the new bridge could be put in

place, the old one had to give way.

A structure from the ‘60s, the bridge

was considered to be at risk of collapse,

and had been closed off to vehicles for quite

a while. Accordingly, the run-down bridge

was removed two months earlier in a night

shift that spanned multiple hours and saw

the old structure lifted out after being split

into eight sections. The Steil team used a

different machine to remove the bridge: a

Terex AC 350/6 all terrain crane. The time

factor proved to be a challenge throughout:

“Since both the old and the new bridges

cross over the Paris-Mannheim ICE train

route, the overhead lines had to be discon-

nected from the grid before the lifts were

carried out. We were asked to disrupt the

Intercity-Express service as little as possi-

ble, this meant that we only had a time win-

dow of a few hours in both cases,” reports

Martin Mittler, who is in charge of resource

planning at Steil and was one of the people

responsible for the project.

The Steil team did not just face a tight

schedule, but also challenging conditions.

The work site was right in the middle of

a residential area, leaving the team with

precious little space and making it diffi-

cult both to get the Superlift 3800 crane’s

components to the site with a total of 19

trucks and to set it up with a Terex AC

350/6 assist crane. “Fortunately, though,

the Superlift 3800 crane is really easy to

transport, and that made our lives a lot

easier. In fact, the modular quick-connect

system, which makes it possible to split the

crane’s basic structure into two parts, was

one of the reasons why the Superlift 3800

was our crane of choice for this project,”

Mittler points out. This enabled crane op-

erators Daniel and Mike Schulz to set up

the lattice boom crane within the allotted

time frame of only two days despite the ad-

verse conditions. The unit was set up with

an LH1 configuration with a 42-metre main

boom, 205 tonnes of superstructure coun-

terweight, and 50 tonnes of central ballast.

However, the working area for the crane

had to first be prepared with red ironwood

crane mats, as the unstable ground would

have otherwise been unable to bear the ma-

chine’s weight.

Once the crane was in place, the crane and

the working area were ready for lifting the

new bridge. The structure was delivered in

two sections and welded on-site, resulting

in a total weight of 70 tonnes, including the

required slinging gear. After the load was

meticulously rigged so that it would be per-

fectly balanced, the power to the overhead

lines was turned off at 11:30 PM and the lift

started: Crane operator Daniel Schulz start-

ed by lifting the bridge, which was rigged at

four attachment points, to a height of 6 m

at a working radius of 26 m, in order to then

swing it over the tracks. He then increased

the working radius to approximately 30 m

by lowering the boom and moved forward

by about 1 m. That’s where the trickiest part

of the lift came in: “We had to set the bridge

down on supports with laser-like precision

to make sure it was in the perfect position.

Thankfully, the Superlift 3800 is the perfect

machine for that kind of precision work, as

it has extremely sensitive controls that let

you apply just the right touch. In the end,

that made the challenge easy to handle,”

says Schulz.

Mittler added his own comments regarding

the crane’s advantages and says “When our

customers hear that we’re using our Super-

lift 3800 crane with its standard fall protec-

tion system, they know that we’re literally

on the safe side during assembly at the site,

which makes coordination much easier and

saves us from having to sort out that type

of detail.” Project Manager Burghard Hass,

who works for the company that fabricat-

ed the bridge – Dillingen-based Stahlbau

Schäfer, was also tremendously happy with

how the lift went and commented, “It was

really something to see, the way the crane

handled the task so magnificently. I mean,

I was astonished when I saw the level of

precision that could be achieved with such

a gigantic piece of machinery.”

The tail end of the lift also went smoothly:

In just ten hours, the Superlift 3800 crane

was disassembled and loaded on trucks in

order to start its journey to its next project

– which, the Steil team is sure, will once

again show just how reliable, powerful, and

versatile the crane is.