Page 5

Our Ref: AA278

Document1

Page 5 of 6

Item 2 – Site Work

Armah Switchgear Ltd to attend site and position the MCC’s in a ground floor location within 30

metres of the offloading position. If this is not the case, we reserve the right to amend our price

accordingly.

The MCC’s would be bolted down to level concrete floor, re-connected and the busbar joints re-

torqued.

We will provide temporary lighting and power for our use.

The Price includes for 3 men for approx 3 working days, accommodation, car hire and travel during

normal working hours.