Previous Page  37 / 88 Next Page
Information
Show Menu
Previous Page 37 / 88 Next Page
Page Background

2

35

Transformers + Substations Handbook: 2014

ited by the surge arrestors) and have a probabilistic characterisation to

allow the analysis of the insulation. In VFTO tests, the voltage levels

used represent exactly those submitted by the equipment during

normal operation in the field.

Since this test had never been performed before, for final reception

of transformers and since there is no standard guide to analyse the

supportability of VFTO, one of the ways to evaluate was by observation

of behaviour of the transformer during the test: evaluating possible

direct disruptions to ground and comparing the results of standard

lightning impulse tests performed before and after the VFTO applica-

tions.

Comparison of VFTO with the standard waves of

lightning impulse

In the comparison shown in

Figure 20

, the frequency of oscillation after

the chop which converges fully with software simulations can be seen.

It is possible to check the reduction of the cut-off when performed

on gas. It is important to point out that the measure point for one or

other condition of wave is the same and was placed at porcelain bush-

ing extremity. However, as the chop happened in a gas enclosure

system, the real time of the chop is much earlier than the time report-

ed by the measurement. This means that it will be a significant increase

in the frequency of this transient applied to the transformer.

Figure 22

shows the increase on current levels owing to the chop

on gas of a waveform of 1 300 kV when compared with a chop on air

of a waveform of 1 705 kV. It can be observed that, although the volt-

age level of the gas chopped wave is 23% lower, the current after the

chop is 185% higher than that chopped on air.

gas in an extremely short time and the generation of correlated freak

of insulation request on high intensity, it was established that the

measure of cut-off time would be performed on the top of porcelain

bushings (see details of chopped points of the wave and details of

measurements in

Figures 14

and

15

).

Therefore, as the chop occurred inside the gas chamber and the

waveform was measured on top of the bushing, there was a delay of

about 250 ns between the real chopped waveform and the measured

waveform.

VFTO application to transformers

After calibrating the chopped device and certifying that the set support-

ed VFTO applications in an independent manner, the device was as-

sembled in the transformer according to

Figures 17

and

18

. That is the

beginning of the test sequence presented in

Table 1

.

During the application of full and chopped waves of an ordinary

lightning impulse test, the gap

of the chopped device on gas

is kept open so as not to per-

mit the chop on the gas. When

VFTO applications are re-

quired, the gap of the chopped

device on air is completely

opened while the gap on gas

(inside the chopped device) is

set according to the previous

calibration.

Measure analysis

It is important to address the

differences in the voltage

levels applied during the im-

pulse test and VFTO. In the

impulse test, the voltage lev-

els are higher than those

submitted during transformer

operation in the field (between

10 and 30% higher, being lim-

Figure 17: Transformer assembled

with chopping device and porcelain

bushing.

Figure 18: Transformer prepared for lightning impulse test, switching and

VFTO.

Figure 19: Comparison voltage – lightning impulse chopped on gas

(1 350 kV) and chopped on air (1 705 kV).

Figure 20: Comparison voltage – lightning impulse chopped on gas

(1 350 kV) and chopped on air (1 705 kV).

Impulse analysing system and

generator control

HV divider

Chopping gap

Impulse generator

Transformer

under test

<On gas chopping time = 2 µs

<On air chopping time = 4 µs

<On gas chopping duration = 250 ns

<On air chopping

duration = 900 ns