Background Image
Previous Page  47 / 64 Next Page
Information
Show Menu
Previous Page 47 / 64 Next Page
Page Background

45

CONSTRUCTION WORLD

MARCH

2015

STEEL CONSTRUCTION

Pylon Pile Cap

An unusual aspect of the project is that

the pile cap for the two main pylons has to

straddle over a bank of high voltage elec-

trical cables. These services were installed

during the expansion of the OR Tambo Inter-

national Airport and did not appear on any

service drawings. Critically they could not

be moved. Rather than redesign the bridge

a bespoke pile cap was designed using a

detailed finite element model.

Aesthetics of engineering

elements

The shaping of the towers was carefully

considered as they are a visually dominant

feature of the footbridge. To create a taper

that appeared intuitively correct the section

tapers in accordance with the golden ratio.

The golden ratio is where two quantities

have the same ratio to each other as the

ratio of their sum is to the larger of the

two quantities. Mathematically, the ratio is

1 to 1,618.

The lower tower section is 13,225 m

long and has a constant diameter. The next

section is a tapering section with a length of

8,175 m, which is 13,225 m divided by 1,618.

The taper is then continued with the same

pattern as shown.

Ingenuity originality and

innovation

It is hoped that the bridge is a testimony

to an engineer’s ability to create original

structures that combine economy with

aesthetics. Unseen ingenuity is perhaps

the integral abutments and connections

that minimise the number of expansion

joints required in the ramps or the complex

interaction between the structure and its

piled foundations.

The deck’s torsion box is also a key

structural element in dealing with the unbal-

anced cable forces at each pair of outriggers.

Innovation within the context of a rational

structural system drove the final form of

the outriggers, which went through many

design iterations.

Responding to needs of

client and community

The most satisfying aspect of the project

is to witness the daily use of the bridge by

thousands of people and the improved space

that commuters now have. It is fulfilling to

see the structural form that is conventional

yet unconventional as such a functional

piece of infrastructure.

The bridge sits in an industrial zone

next to the airport and stands apart from

its surrounding to some degree. In doing

so it acts as a visual marker for pedestrians

heading to and from work. The intent with

the leaning towers was to give the structure

a dynamic feel that reflects the urgency of

the commuters who hurry across it. The

architecture of the bridge also responds to

the adjacent international airport.

The urban planning inputs to link the rail,

taxi and pedestrian transport modes played

a large part in the structure’s final form.

Significant effort was invested in concep-

tualising the functionality of the bridge

to ensure it can be used and accessed by

all. Safety and security concerns were also

mitigated by providing multiple access and

egress points.

Planning and technical

design planning

From previous experience the design team

was aware of the importance of trans-

lating the original design intent through

the detailed design stage and onto the

engineering drawings. The innovative

step of producing a design intent booklet

with sketches illustrating the look and feel

of components and swatches of the pre-

ferred materials was developed and main-

tained. This helped team members focus

of the desired outcomes during the various

design iterations.

Meeting the client’s

deadlines for readiness

The project experienced delays due to

the discovery of underground services.

However, the carefully considered construc-

tion sequence and temporary works designs

meant that pedestrian access across the

R21 was maintained throughout the

construction period.