20
Mechanical Technology — March 2015
⎪
Power, energy and energy management
⎪
R
oyal HaskoningDHV was
appointed in 2010 to carry
out the environmental im-
pact assessment (EIA) for
the R5‑billion ACWA Power Solafrica
Bokpoort Concentrated Solar Power Plant
to be situated at Bokpoort, 25 km north
of Groblershoop in the Northern Cape.
Royal HaskoningDHV was also ap-
pointed to carry out two basic assessment
processes for the water supply pipeline
from the Orange River. The position of
the first extraction point was deemed to
be unsuitable due to the Orange River’s
flood patterns and this necessitated the
selection of a second extraction point and
a 3.0 km pipeline extension. In 2013,
Royal HaskoningDHV was appointed as
the environmental control officer (ECO)
at the start of project construction, a pro-
cess that concludes in December 2015.
The approved EIA is for a 75 MW
CSP Plant and currently a 50 MW plant
is being constructed utilising parabolic
trough technology, which is the more
suitable CSP technology option for the
environment, especially avifauna (bird-
life). Malcolm Roods, market segment
CSP parabolic trough technology is the more suitable CSP
technology option for the environment, especially avifauna.
The Bokpoort CSP plant is suitable for base load generation because huge molten salt storage tanks are
used to generate electricity for up to 9.3 hours during the night.
The ACWA Power Solafrica’s new Bokpoort
Concentrated Solar Power (CSP) Plant is
being built to supply renewable solar
energy into Eskom’s grid to alleviate
the country’s power crisis. At the same
time, it will satisfy one of the National
Development Plan’s most crucial agendas:
job creation in impoverished areas.
EIAs and the R5-billion Bokpoort CSP plant
leader, environmental services at Royal
HaskoningDHV says when applying for
an EIA it is important to ensure that the
application is for a large enough area;
and that the maximum capacity, together
with all relevant EIA listed activities, are
applied for. “This allows for phased de-
velopment should it be adopted, as with
the Bokpoort development where another
25 MW generating capacity could be
added at a later stage”.
He adds that it is crucial to have as
much detailed engineering information
as possible when conducting the EIA
process. “It is also important to listen to
local knowledge,” he advises, adding that
the environmental assessment took 11
months to complete while the basic as-
sessment process took only four months.
Roods believes that these good
timeframes were only achieved with
the help of the National Department of
Environmental Affairs, which assisted in
achieving a much faster turnaround time,
and that they should be commended
for this.
“It is also important to involve all the
relevant and affected stakeholders during
the public participation process: Transnet
and Eskom, among others.”
Elton Julies, HSEQ manager ACWA
Power Africa Holdings, says, “Bokpoort
is different from other solar projects in
that we can generate electricity from the
solar power system during the night.
We have 9.3 hours of storage capacity
suitable for base load generation. The
heat from the huge salt storage tanks is
used to generate electricity for up to 9.3
hours at night.”
Some of the project challenges include
a 25 km dirt road to the site, which
is subject to increased traffic volumes
during construction. By far the greatest
challenge is waste management during
construction – both hazardous and gen-
eral waste – which is exacerbated by the
remoteness of the site and the limited
number of licensed waste sites in the
Northern Cape.
Acting as environmental control of-
ficer for the project, Roods, says, “The
main purpose of the monthly compli-
ance audits is to ensure that all relevant
environmental conditions prescribed