Kolter Homes Policies and Procedures

Policy No. 5.5.4 Lot Unique Budget Adjustment

Page 2 of 2

- Construction Manager can refer to the community / phase level worksheet prepared with the Project

Director.

- Construction Manager uses the Pre-Start Review Form (Lot Unique Budget Form).

o

Prints Start Request.

o

Review plot plan against Master Drainage Plan and meets with the grading contractor to

calculate any haul off or fill.

o

Review plot plan against Landscape Plan for street trees, corner lots, etc.

o

Review plot plan against Sidewalk Plan.

o

Construction Manager must walk site to verify existing trees and document possible utility

issues.

o

Meets with Project Director / VP to discuss any additional landscape.

- Construction Manager completes the job site conditions review process, which includes the revised

quantities take-offs.

o

Construction Manager provides the Purchasing Coordinator with a copy of both the signed plot

and job site condition form by email.

o

Construction Manager shall scan copy of the job site conditions to the share drive for archival

purposes.

o

Construction Manager shall place a copy in house file.

o

Should an issue arise that would delay the permitting process, the Construction Manager must

email the Project Director / VP, Area Construction Manager and Permitting Coordinator

immediately, and note the issue in the subject line/title of the email.

Permitting Coordinator:

- Updates the Production Report tool as complete.

Purchasing:

- Purchasing Coordinator will contact Construction Manager if Job Conditions worksheet is not returned

at least 15 days before the scheduled PO release date in the Production Report tool.

- Purchasing Coordinator updates quantities in Newstar and adjust soft cost budget

- Purchasing Coordinator notifies trades affected that their budgets for that lot / block will be adjusted

manually and no ePO’s will be required by the field.

-

For items that are estimated, such as dirt work, the lot unique budgets will be updated and an ePO

should be issued to the vendor by the Construction Manager.