Background Image
Previous Page  38 / 92 Next Page
Information
Show Menu
Previous Page 38 / 92 Next Page
Page Background

36

CONSTRUCTION WORLD

OCTOBER

2015

ROADS AND BRIDGES

The system was recently used on

a major SANRAL road upgrade

contract in Ballito, one of the first

and largest local applications of the

system to date. Project engineers, SMEC South

Africa, were involved in the detailed design

of the system and realised a number of cost

benefits on the project by using the Tensar

TW1 System.

The scope of works entailed the widening

of a two-lane, single carriageway to a three-

lane, dual carriageway in Ballito, about 40 km

north east of Durban. Due to the site’s undu-

lating topography, earth retaining structures

had to be built to bring the extra lanes to level.

The lane widening had to be constructed

within the road reserve to eliminate encroach-

ment into existing developments. To reach

this objective, two near-vertical, Mechanically

Stabilised Earth (MSE) walls of 11 m and 5 m,

covering a total length of over 400 m, and

2 000 m

2

, were proposed.

MSE walls, broadly, consist of fill material

with horizontal layers of reinforcing elements

which may take the form of sheets, grids, strips

or meshes. The reinforcing elements, which are

either metallic or polymeric, are able to sustain

tensile loads and the effects of deformation or

soil strains developed in the fill, part of which

is transferred to the clad face through some

form of positive connection.

Following a competitive tender process,

the tender for construction of the project was

won by Afriscan Construction, which included

the use of the Tensar TW1 system. The project

consulting engineers were satisfied that the

system would meet the technical require-

ments and were subsequently closely involved

in the detailed design of the system.

The intricate design needed to ensure

that the system complied with internal

and external stability and project technical

requirements. A benefit of the system was

that lower quality fill, which was more readily

available and less expensive, could be utilised

as the grids provide greater coverage and soil

adherence than other systems on the market

and the product is also not prone to degrada-

tion or chemical attack by natural soils.

A further benefit to the system was that

adjacent landowners were satisfied that the

appearance of the split-face blocks would

provide a high aesthetic appearance which

would complement the local architecture.

Tensar TW1 System

The system, developed by Tensar Interna-

tional of the UK, comprises the specially

designed TW1 block, combined with high

density polyethelene (HDPE) grid mats –

known as Tensar uniaxial geogrids – that

are attached by a special connector into the

blocks and extend horizontally to secure and

reinforce the fill, thereby turning the whole

structure into a monolithic mass.

The positive connection to the cladding

or split-block face is an important attribute

of the system and allows it to be used on

near-vertical walls exceeding 7 m; which is

the present maximum height attainable with

other retaining systems available locally.

Internationally, maximum tiered wall

heights of 60 m have been achieved with

the TW1 system, with a maximum single tier

height of 22 m in Fujairah, UAE.

Geotechnical investigation and

design

As this was one of the first of these walls in

the country, the design of the wall was a close

collaborative effort between Kaytech, Tensar

and SMEC South Africa. SMEC undertook

the final design checks to ensure overall

stability of the system and compliance with

project specifications and local codes. These

included integration of the system with the

new roadway and New Jersey barriers along

the top of the wall, as well as cognisance of

the overall geotechnical conditions.

Design optimisation

A key consideration in the design was to

ALTERNATIVE

to

TRADITIONAL

retaining wall options

Introduced into the South African market by Kaytech,

the Tensar TW1 System was developed as an alternative

to traditional retaining wall options and has been used

extensively in Europe and elsewhere internationally.

optimise the use of lower quality fill material,

whilst simultaneously minimising the amount

of lateral support required in cutting back

and benching into the existing roadway, i.e.

the back excavation slope. Limited space

was available for the 11 m high wall, which

restricted the length of the strips to 7 m. At the

same time it would be beneficial to the project

if Berea sands could be utilised. However, by

using the lower quality fill, strip lengths would

need to be increased, which implied either

increased cut or the use of a near vertical back

excavation slope requiring the use of shotcrete

and ground anchors or nails.

After a number of iterations, the final

design for the 11 m high wall comprised the

use of 7 m long strips, a granular (COLTO

G6) backfill for most of the height and 1 m

thick granular soil-raft foundation. No lateral

support was thus required and conventional

benching into the existing fill was utilised. For

the upper 3 m of the 11 m wall and for the 5 m

high wall, Berea sand was used throughout.

Construction

Some of the further benefits of the Tensar

TW1 System are that it is labour-intensive

and eliminates the need for cranes and other

heavy lifting equipment. Additionally, the

TW1 block is manufactured locally by

Remacon, a Tensar licensee, for that s

pecific block manufacture.

In utilising the new system a number of

challenges were experienced during construc-

tion. These included: the setting of the base

block, which is key to achieving the final face

inclination of 86°; compaction criteria;

stormwater control; and the use of labour

inexperienced in building these walls.

However, these problems were quickly

resolved through close collaboration between

the contractor, consultant and supplier.

The Kaytech and Tensar teams were able to

provide technical assistance to the contractor

and consultant’s supervising team with

regards to installation, testing standards and

quality control and assurance.

Conclusion

The project has showcased the level of

knowledge and experience required to design

and construct a Tensar TW1 Mechanically

Stabilised Earth Wall. This has been a major

achievement for Kaytech, considering this is

the first wall of this size to be constructed in

South Africa. The system provides a number of

benefits over other block and other Mechan-

ically Stabilised Earth systems, including:

the effective connection between block and

geogrid; a near-vertical face inclination; locally

manufactured blocks; aesthetic appeal; labour

intensive construction; and eliminating the

use of heavy lifting equipment.

>

Tensar Polyethylene RE560 uniaxial geogrid.

36

I