Background Image
Previous Page  8 / 64 Next Page
Information
Show Menu
Previous Page 8 / 64 Next Page
Page Background

6

MODERN MINING

July 2015

MINING News

Diesel Power awarded

Elandspruit contract

Wescoal Mining has appointed Diesel Power

Open Cast Mining as the mining contractor

for its new Elandspruit mine near Middelburg

in Mpumalanga. Mining activities have com-

menced and Elandspruit will produce its first

Run of Mine during July 2015.

The mining division is on track to produce

approximately 335 000 tons of Run of Mine

(ROM) per month during the final quarter of

the current financial year. This is equivalent

to approximately 4 Mt ROM on an annualised

basis.

TheWater Use Licence for Elandspruit was

secured early this year and the official open-

ing of the mine will take place in August.

The facility will eventually double Wescoal’s

mining output and is fundamental to the

continued growth, sustainability and profit-

ability of the Group with 80 per cent of its

production supplied to Eskom through long-

term contracts.

Canada’s True Gold Mining Inc, listed on

the TSX-V, which is developing the Karma

gold project in Burkina Faso, reports it

has drawn down an additional US$14 mil-

lion of the US$100 million financing from

Franco-Nevada (Barbados) Corporation

and Sandstorm Gold Bank Ltd. This is

the third draw down that True Gold has

made under the facility, bringing the total

True Gold’s Karma site now a hive of activity

amount drawn to US$71,6 million.

True Gold says that construction at

Karma remains on schedule with the

planned placing of ore on the heap leach

pads in early 2016 and first gold pour

anticipated for the end of Q1-2016.

Christian Milau, President and CEO of

True Gold, stated, “There is an atmosphere

of excitement on site with a workforce of

over 500 focusing on earthworks and

the processing plant final assembly.

We have progressed rapidly with

site development and construction,

highlighted by commissioning of

the mine fleet, completion of the

raw water pond excavation and ini-

tial construction of the raw water

pipeline.”

Excavation of the Pregnant Leach

Solution (PLS) pond has commenced,

stripping of Cell 1 of the heap leach

pad has been completed and assem-

bly of the hard rock crusher has

begun. Assembly of the Absorption,

Desorption and Refining (ADR) plant

structural steel has also started. The

mine fleet of six Komatsu 785 trucks,

a PC 3000 excavator and a WA800

loader has been commissioned.

Located 185 km north of Ouaga­

dougou, Burkina Faso’s capital, Karma

is a technically simple open-pit, heap

leach mine which will produce an average

of 97 000 ounces a year over an eight-

and-half-year mine life (although further

phases of development are anticipated).

The project has a capex of US$131,5 mil-

lion with the estimated payback period

being just 16 months. South Africa’s SENET

is the EPCM contractor.

Construction underway at Karma late last year. The site has progressed considerably since then (photo: True Gold).

Employees receive training on one of the newly commissioned Komatsu 785 haul trucks. The mine has a

fleet of six of the trucks (photo: True Gold).