Previous Page  50 / 72 Next Page
Information
Show Menu
Previous Page 50 / 72 Next Page
Page Background

48

CONSTRUCTION WORLD

JUNE

2016

ROADS AND BRIDGES

engineer on how to move forward with

the project.

Basil Read provides the Client with

alternatives such as providing a concrete

(rigid) alternative to the proposed bitumen

pavement (flexible).

Unfortunately road construction (and

infrastructure in general) is generally based

on current economic imperatives: our forecast

is about four to five years. Some clients (such

as concessionaires and certain roads agen-

cies) can take a long term view and invest in

concrete roads – these last longer, but are

initially more expensive.

The St Helena Airport runway is a

concrete runway – there the imperatives were

different: not based solely on initial infra-

structure cost, but how to maintain a runway

over the long term in a very remote location.

What is the division’s unique

selling point Price? Technology?

Our ability to offer alternatives to the design

that we are presented with, is a unique selling

point. Price can be a unique selling point in

a competitive market, but in the long run,

clients then allow contractors to build inferior

products because they use the cheapest price

as a unique selling point.

On a building, inferior construction can

be spotted early on. It is very hard to build a

road that fails within six months – some of

our international clients and roads agencies

are learning this the hard way: the saving they

initially regarded as beneficial often results in

an inferior product.

Our diverse team is another unique

selling point. We have the expertise within

the company to try and find a solution. This is

the direction the Division is moving towards

– solutions driven – where construction

and engineering move closer together and

one does not simply provide a client with

a product that they decided upon as their

solution very early in the process and without

input from the contractor on constructability

and cost efficiency issues.

What is your opinion of

the current status quo of

construction?

It is a concern that the rollout of infra-

structure projects is not happening faster

throughout southern Africa. Infrastructure

provision is one of the ways to stimulate

an economy. Added to that is the fact that

wealth in the broader African context cannot

be created when there is a lack of reliable

transportation links – it is a continent with

tremendous wealth, but these resources are

landlocked and can often not be transported

to a port.

It is a tough time in the construction

industry – we are, hopefully, at the end of a

long negative cycle. There is opportunity in

this though – it allows Basil Read to refor-

A recently completed project is the

rehabilitation of Bruma Lake – Basil Read Roads

Division is currently doing load testing of the

reconstructed bridge.

Project: Upgrade of National

Route 61 section 7 from Baziya

to Mthatha

• Client: SANRAL

• Duration: 36 months

• Value: R504 103 892

• Scope: Widening to a 13,4 m surfaced

width, additional auxiliary lanes, 14

major culverts, etc.

Project: Marine works for the

Admin Craft Basin at the Port

of Ngqura

• Client: Transnet Capital Projects

• Duration: 20 months

• Value: R376 158 453

• Scope: Preparation of Eastern

Reclamation Site to receive land based

excavated material, excavation and

dredging of approximately 656 00 0m³

of material.

Current major projects

Project: Ashton to Montagu

road (13,4 kms) in the Western

Cape

• Client: Western Cape Government:

Department of Transport and Public

Works

• Duration: 36 months

• Value: R583-million

• Scope: Rehabilitation of TR 31

from Ashton to Montagu through

Cogmanskloof, the reconstruction and

widening of the existing pavement

layers, three of the existing river

bridges are to be replaced with new

structures, the stormwater systems are

to be upgraded, retaining walls on both

the mountain and river side of the road

will have to be installed.

mulate the way we do business and to start

working closer to the client instead of being

reactive and relying on work to come our

way: the St Helena Airport project is an

example of this – we actively ‘created’ work

on a design and construct basis. Through

projects undertaken within our Developments

Division we have a model to create work

across the company.

Locally South Africa has an immense

need for housing, sanitation and water

supply. Housing is one sector that will

develop work for the company as a whole and

which we are very excited about.

Project: Polokwane Eastern

Ring Road Phase II

• Client: SANRAL

• Duration: 36 months

• Value: R641-million

• Scope: Re-Alignment of the N1-27

towards the south of Polokwane

over 4,2 km, development and

widening of the N1-27 ring road as

a four lane divided dual carriageway

over 19 km, and construction of six

new bridges.

Project: National Route 1

section 29: Construction of

the Musina Ring Road

• Client: SANRAL

• Duration: 30 months

• Value: R556-million

• Scope: Construction of a 4 lane dual

carriageway Greenfields bypass of

approximately 8 km, Construction

of the Musina interchange and

Freedom Street overpass and

Nancefield (R572) Interchange,

Construction of Toynton Road and

the Mac Transco railway line road-

over-rail-bridge, re-alignment and

construction of Harper road.