Background Image
Previous Page  27 / 64 Next Page
Information
Show Menu
Previous Page 27 / 64 Next Page
Page Background

89 km 400 kV transmission line – great achievement

Amajor milestone for the

CONCO group

is the three-year construc-

tion of a 400 kV, 89 kilometre long transmission line for Eskom,

stretching from Eros substation near Harding in KwaZulu-Natal,

towards Vuyani substation in Mthatha in the Eastern Cape. This

major project was completed by CONCO and officially handed

over to Eskom last year. Commenting on the success of the pro-

ject, Sugan Naidoo (Eskom project engineer) says, “The CONCO

relationship with Eskom was professionally handled with Eskom's

requirements being met in terms of delivering the project accord-

ing to specifications.The contract management was executed with

excellence.The handover was well received by Eskom for the first

section of transmission line being built in the formerTranskei area

which is now part of the Eastern Cape,” said Naidoo. “CONCO built

89 kilometres of the 167 kilometre 400 kV line and considering this

was CONCO's first 400 kV line construction project, its successful

completion was a great achievement by the efforts of the project

team and site workers.”

CONCO project engineer, Joseph Mahlangu says, “Effective

stakeholder communication and project control integration which

encompassed communication planning, applying best practised

systems and controls, work structure, scheduling, reporting and

adhering to the project plan, were key elements to the project's suc-

cess.”This is the first 400 kV line in the formerTranskei area enabling

a higher power transfer capability in the area. “400 kV Lines transmit

bulk power to feed a large number of customers and can power

up a town,” says Naidoo. “When the line is placed in commercial

operation, the current power shortfall in the Mthatha area and sur-

rounding towns will be relieved and will strengthen the network

by supplying sufficient capacity to the area for economic growth.”

Approximately 400 people worked on the project over a three-year

period. During that time, over 200 temporary employment oppor-

tunities were created in the local villages. CONCO also donated

200 desks, 100 chairs, a microscope and a projector, to Dudumeni

High School in Flagstaff.

“The Eros/ Vuyani project is a milestone for the CONCO group,”

says Mahlangu. “It's the first 400kV project executed by CONCO

and we have proved our ability to project manage, engineer and

construct a transmission line of this dimension. We completed it

on time, within budget and to the highest quality.”

Enquiries: Joseph Mahlangu.Tel. 011 805 4281 or email

joseph.mahlangu@concogrp.com

Proper integration of test joints in external thermal insulation composite systems

The relevant technical processing guidelines for insulation materi-

als must be observed for the thermal insulation of existing or new

buildings with external thermal insulation composite systems (ET-

ICS). This also impacts the integration of windows, doors and all

components leading through the composite system. In addition,

these guidelines are relevant for lightning protection components.

Lightning protection systems, in conjunction with an external ther-

mal insulation composite system, pose challenges for designers and

installers, particularly with regard to the installation and integration

of test joints for these systems. The test joint products previously

available on the market were often installed on the roof level or in

flush-mounted boxes, exposing them to increased pollution. The

expandable test joint box for external thermal insulation composite

systems from

DEHN

is an innovative product for designers and

installers which allows for flexible and proper installation.

The telescopic test joint box can be gradually adjusted for insula-

tion material thicknesses between 90 and 140 mm and can therefore

be used for common insulation material thicknesses. An additional

spacer must be used for insulationmaterial thicknesses between 140

and 320 mm.The spacer has a Styrofoam core to prevent thermal

bridges and can be shortened from 200 to 50 mm in 10 mm interval

steps.The down and earthing conductor can be easily led into the

box, and there is sufficient space for installing a clamp.Thanks to

the test joint box’s dimensions of 140 by 180 mm and a depth of 80

mm, continuity and earthing measurements for lightning protec-

tion systems can be

easily performed by

means of measuring

callipers. The proper

installation is finished

by mounting a stable

and aesthetically ap-

pealing stainless steel

cover, which protects

the test joint from

rain.

A UV and weath-

er-resistant foam seal-

ing is integrated in

the cover to ensure

that the test joint is

fully protected, whilst

the edge of the cover

exerts sufficient pres-

sure on the sealing at the corners. This test joint box for external

thermal insulation composite systems is an innovative, universal

and practical solution for integrating a test joint in external thermal

insulation composite systems.

Enquiries: Alexis Barwise.Tel. 011 704 1487 or email alexis.barwise@

dehn-africa.com

ELECTRICAL PROTECTION + SAFETY

CONCO chief executive officer, David van Zyl,

hands over a plaque to Eskom executive projects

manager, Bob Naraghi, at the official handover.

25

April ‘15

Electricity+Control