Local Fuel PLC – The Shoreham Oil Terminal
SIS Management of Functional Safety – Safety Plan
P & I Design Ltd
DOCUMENT NO:LF364004_RPT
2 Reed Street, Thornaby, UK, TS17 7AF
ISSUE: D DATE: 07.06.16
Tel: + 44 (0)1642 617444
PAGE 17 OF 28
Fax: + 44 (0)1642 616447
www.pidesign.co.uk12.2 SIS Installation, Commissioning and Validation Action History
12.2.1 SIS Test Procedures
Activity History – Terminal in Texaco/Chevron/Valero ownership
Date
Reference
Description
Roles
Persons assigned
10.04.08
18
SI157035_RPT
Revision A
SIS Panel FAT
Procedure -
Original Issue
P&I Design
Ltd
D S Regan BEng
D R Ransome
09.07.08
18
SI157035_RPT
Revision B
SIS Panel FAT
Procedure – Panel
Test
P&I Design
Ltd
D S Regan BEng
D B Faulkner
22.10.13
18
SI157035_RPT
Revision C
SIS Panel FAT
Procedure
P&I Design
Ltd
D S Regan BEng
D B Faulkner
26.03.08
SI157036_RPT
Revision A
SIS Shutdown
Conditions
Functional Test
Procedure –
Original Issue
P&I Design
Ltd
D S Regan BEng
D R Ransome
17.11.08
SI157036_RPT
Revision B
SIS Shutdown
Conditions
Functional Test
Procedure –
Tankside Valves
Removed
P&I Design
Ltd
D S Regan BEng
D R Ransome
27.07.12
SI157036_RPT
Revision C
SIS Shutdown
Conditions
Functional Test
Procedure – Wet
Testing Added
P&I Design
Ltd
D S Regan BEng
D B Faulkner
30.07.12
SI157036_RPT
Revision D
SIS Shutdown
Conditions
Functional Test
Procedure – Wet
Testing Corrected
P&I Design
Ltd
D S Regan BEng
D B Faulkner
28.04.08
SI157037_RPT
Revision A
SIS
Documentation &
Hardware
Verification Test
Procedure –
Original Issue
P&I Design
Ltd
P Lynch
D R Ransome
09.05.11
SI157037_RPT
Revision B
SIS
Documentation &
Hardware
Verification Test
Procedure – 2011
Testing Update
P&I Design
Ltd
P Lynch
D S Regan BEng
08.06.12
SI157037_RPT
Revision C
SIS
Documentation &
Hardware
Verification Test
Procedure – 2012
Testing Update
P&I Design
Ltd
P Lynch
D S Regan BEng
26.03.08
SI157038_RPT
Revision A
SIS Power Failure
Functional Testing
Procedure –
Original Issue
P&I Design
Ltd
D S Regan BEng
D R Ransome
17.11.08
SI157038_RPT
Revision B
SIS Power Failure
Functional Testing
Procedure –
Tankside Valves
Removed
P&I Design
Ltd
D S Regan BEng
D R Ransome
23.07.12
SI157038_RPT
Revision C
SIS Power Failure
Functional Testing
Procedure – Tank
3 Relay No
Corrected
P&I Design
Ltd
D S Regan BEng
D R Ransome