GAZETTE
AUGUST/SEPTEMBER
1994
them by the 1935 Act. (2) The executive
could agree to indemnify the local
authority against the cost of observing
the requirements of the 1935 Act, but
such an agreement could not in any way
limit or reduce the statutory obligations
of local authorities or the minister. Thus
budgetary and financial constraints
could not afford an answer to those pro-
ceedings. If the executive wished to
limit or reduce such obligations it
would have to seek the enactment of
appropriate legislation by the Oireach-
tas. (3) S. 31 of the Civil Bill Courts
(Ireland) Act 1851 as adapted did not
apply to the present Circuit Court. It
had been impliedly repealed, first of all
by the creation of the Circuit Court un-
der the Courts of Justice Act 1924, and
subsequently by the Courts (Estab-
lishment and Constitution) Act 1961.
Thus the orders purporting to adapt s.
31 and the order of 23 June 1992 pur-
porting to delete Drogheda as a Circuit
Court venue were of no effect. In any
event these orders had not been made
to regulate the sittings of the Circuit
Court but to provide a defence to the
present proceedings and for that reason
they were void. (4) The events preced-
ing the order of the President of the
Circuit Court suggested that the only
reason for the omission of Drogheda
from the list of towns where the Circuit
Court was to sit was the service of the
dangerous buildings notice in respect of
the Drogheda courthouse. (5) The
county council were obliged under s. 3
of the 1935 Act to provide suitable ac-
commodation as directed by the minis-
ter. They were not bound to maintain
the same courthouse building and were
entitled to abandon an old or dilapi-
dated building provided that they
made available suitable alternative ac-
commodation for the sittings of the Cir-
cuit Court.
Reported at [1994] 1 ILRM 334
David Manning v. John R. Shackleton
and Cork County Council (notice
party): High Court (Barron J) 1 April
1993
Judicial Review - Reasons for decision -
Fair procedures - Arbitration - Compul-
sory purchase order made in respect of ap-
plicant's lands - Question of assessing ap-
propriate compensation - Property arbitra-
tor appointed - Whether obligation on arbi-
trator to provide a breakdown of the reasons
for his award - Whether question of costs
should be remitted to arbitrator - Acquisi-
tion of Land (Assessment of Compensation)
Act 1919
, ss.
3(3), 5(1) and 6(1) - Arbitra-
tion Act 1954, s. 36
Facts The applicant owned lands at
Barryscourt, Co. Cork, a portion of
which became the subject matter of a
compulsory purchase order made by
Cork County Council in 1986. The re-
spondent was appointed to arbitrate the
measure of compensation to which the
applicant was to be entitled. Cork
County Council then made an uncondi-
tional offer of £175,000, exclusive of
costs, in full and final settlement of the
applicant's claim. The offer also in-
cluded an undertaking to carry out cer-
tain accommodation works and further
such undertakings were given by Cork
County Council during the course of
the arbitration hearing. On 12 Decem-
ber 1991 the respondent made an award
of £156,280. As the award did not ex-
ceed the offer which had already been
made, the applicant was ordered to pay
the costs from the date of the offer. The
applicant's solicitors subsequently
wrote to the respondent requesting that
he furnish the applicant with a written
judgment setting out his findings of fact
and of law as well as a breakdown of the
content of the award. The respondent
replied by letter that he was not re-
quired to give a written considered
judgment. By order dated 27 July 1992,
the applicant was given leave to seek
judicial review of the respondent's
award.
Held by Barron J in refusing the relief
sought in respect of the giving of rea-
sons and remitting the matter to the
respondent for the determination of is-
sues pertaining to the award of costs: (1)
The giving of reasons by a person or
body required to act judicially may be
compelled by the High Court when
such reasons are necessary to determine
whether such a power has been validly
exercised. It is not an essential obliga-
tion and arises only when required to
prevent an injustice or to ensure that not
only has justice been done but is seen to
have been done. However, the appli-
cant had not indicated how he was
likely to suffer prejudice or injustice as
a result of the failure to state reasons. (2)
If the applicant had wished to ensure
that, contrary to the normal practice, the
respondent should give reasons for his
award, he should have made a submis-
sion to that effect at the outset of the
hearing. By allowing the hearing to con-
tinue and by failing to seek reasons
from the respondent to be inserted in
the award, he accepted the normal prac-
tice. (3) The applicant had to be taken to
know how the award was broken up
between the heads of claim. So far as
these amounts were dependent upon
fact, the award was final and binding
upon him. So far as there may have been
legal issues which the respondent had
determined, the applicant could have
brought these before the High Court by
asking the respondent to make his re-
port in the form of a special case under
s. 6(1) of the Acquisition of Land (As-
sessment of Compensation) Act 1919,
but he had not done so. The applicant
had likewise waived his right under s.
3(3) of the 1919 Act to require the re-
spondent to specify the amount
awarded in respect of any particular
matter. (4) In relation to the issue of
costs it appeared that the amount of
compensation which was awarded
might have been affected by the nature
of the undertakings given by the notice
party. It would not be possible to say
whether the award was more or less
than the unconditional offer until there
was a determination as to the amount,
if any, which the respondent deducted
from the compensation by reason of the
undertakings which were given in the
unconditional offer and were added at
the hearing. Accordingly the matter
should be remitted to the respondent
for a determination of these issues. In
any event this was a ground for remit-
ting a matter to an arbitrator under s. 36
of the Arbitration Act 1954.
Reported at [1994] 1 ILRM 346
Garden Village Construction Co. Ltd
v. Wicklow County Council: High
Court (Geoghegan J) 1 October 1993
Local Government - Planning and Devel-
opment - Works carried out outside bound-
ary line on map attached to permission -
Application for extension to planning per-
mission refused - Whether refusal based on
misinterpretation of statute - Whether un-
authorised development - Local Govern-
ment (Planning and Development) Act
1963, s. 26(10) - Local Government (Plan-
ning and Development) Act 1982, s. 4
Facts The applicant, a property devel-
opment company, was granted outline
planning permission for a large hous-
ing development of more than 500
houses at Newtownmountkennedy in
Co. Wicklow and subsequently was
granted three planning permissions in
relation thereto. The applicant having
built a small number of the houses car-
ried out substantial works 'pursuant to
such permission' involving,
inter alia,
the installation of a sewage treatment
plant and sludge drying beds, and the
securing of water and electricity sup-
plies. Although it was common knowl-
edge that substantial works had been
carried out, these works were per-
formed outside the red line boundary
2




