Gran Canaria send out increase

General Information

Promoter

Gascan

Operator

Gascan

Host Country

Spain

Status

Planned

Website

Publication Approval Status

Approved

Sponsors

Gascan

100%

LNG-N-165

Project

LNG Terminal

Non-FID

Update Date

19/05/2016

Non-Advanced

Description

this projects consists in the increment of the regasification capacity of Gran Canaria LNG Terminal, up to 225.000 m3(n)/h

Regulatory Decisions and

similar material conditions

Capacity Increments Variant For Modelling

Point

Operator

Year

From Gas System To Gas System Capacity

Gran Canaria LNG

(QDJiV 6 $

2026

LNG_Tk_ESc

ESc

20.9 GWh/d

Comment: The earliest date estimated for the commissioning of this project is 2026.

Gascan

2026

LNG_Tk_ESc

ESc

20.9 GWh/d

Comment: The earliest date estimated for the commissioning of this project is 2026.

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM

Page 148 of 620

Current TYNDP : TYNDP 2017 - Annex A