Expected Gas Sourcing

LNG (HR), It will be gas from Croatia transport system, Croatian UGS and Croatian planned LNG terminaland Baumgarten via Slovenia

Time Schedule

Grant Obtention Date

Delay Since Last TYNDP

The start of the construction has been postponed until 2020.

Delay Explanation

It depends on the agreement with Republika Srpska (B&H)

PCI Details

PCI Benefits

Project changes the capability to transmit gas across the borders of the member states concerned by at least 10%, compared to the situation

prior to the commissioning of the project, Project concerns investment in reverse flow capacity

General Criteria Fulfilled

No

Specific Criteria Fulfilled

Competition, Market Integration, Security of Supply, Sustainability

Specific Criteria Fulfilled Comments

The project is fullffilling and the folloving criteria: Lifting isolation for Bosnia and Herzegovina, reducing bottelnecks, will improve remaining

flexibility, will enable source and route diversification

Pipelines and Compressor Stations

Pipeline Section

Pipeline Comment

Diameter (mm) Length (km) Compressor Power (MW)

Slobodnica - Bosanski Brod

4 million m3 daily

700

6

Total

6

Schedule

Start Date

End Date

Pre-Feasibility

Feasibility

FEED

Market Test

08/2016

Permitting

01/2011

01/2019

Supply Contracts

FID

12/2017

Construction

01/2018

01/2019

Commissioning

2019

2019

NDP and PCI Information

Part of NDP

Yes (2017-2026)

NDP Number

1.13

Currently PCI

No

CBCA Decision

No

Market Survey

Not Relevant (no CBCA decision)

Third-Party Access Regime

Considered TPA Regime

Regulated

Considered Tariff Regime

Regulated

Applied for Exemption

No

Exemption Granted

No

Exemption in entry direction

70.00%

Exemption in exit direction

30.00%

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM