Immingham Storage Co Ltd – Immingham East Terminal
IME-SIS1 – Safety Instrument System Equipment Failure Proof Testing Procedure
P & I Design Ltd
DOCUMENT NO: SI483019_RPT
2 Reed Street, Thornaby, UK, TS17 7AF
ISSUE: A DATE: 09.04.14
Tel: + 44 (0)1642 617444
PAGE 16 OF 19
Fax: + 44 (0)1642 616447
www.pidesign.co.uk8.2
Tank 564 As Left Functional Testing Continued…
Step
Method of Test
Acceptance Criteria
Pass (
)
Fail (x)
Initial
8.2.9
Release HS564 Tank 564 Isolation
Pushbutton.
FINAL ELEMENT valve
automatically reopens initiating
DIAGNOSTICS as detailed on
SI483012_SCH Sheet 1
Comment differences from SCH in
section 8.2.12.
8.2.10
Operations to initiate Terminal Shutdown
system.
Record method of test
……………………………………….
Correct FINAL ELEMENT valve
position and DIAGNOSTICS as
detailed on SI483012_SCH Sheet
1.
Comment differences from SCH in
section 8.2.12.
Time from test initiation to trip
activation <=2 seconds.
Comment failures in section 8.2.12
8.2.11
8.2.8
Operations to Reset Terminal Shutdown
system.
FINAL ELEMENT valve
automatically reopens initiating
DIAGNOSTICS as detailed on
SI483012_SCH Sheet 1
Comment differences from SCH in
section 8.2.12.
8.2.12
Comments/Defects/ Remedial Actions
– Report ALL to System Keeper
Tested by
Position
Qualification
Sign
Date
System Keeper Acknowledgement
(Note: Signature confirms System keeper is advised of Comments/Defects/Remedial Actions and will initiate
terminal procedures for rectification works and/or isolation of plant as required)
Accepted by
Position
Qualification
Sign
Date