Immingham East Terminal – Gasoline Overfill Protection

Safety Instrument System

P & I Design Ltd

DOCUMENT NO: SI277001_RPT

2 Reed Street, Thornaby, UK, TS17 7AF

ISSUE:

F

DATE: 31.10.14

Tel: + 44 (0)1642 617444

PAGE 3 OF 29

Fax: + 44 (0)1642 616447

www.pidesign.co.uk

1

REVISION HISTORY

Rev Description

A

Original Issue – Modification requested, assessed and initiated

B

Revised with extra tanks

C

Tank 709 removed, SIS modified following client discussions

D

Following Stage 3 FSA

Pipeline Valves Declassified as SIS

E

Tank-side Valve XV56701 Installed

2

SCOPE

This document has been prepared for the Safety Instrumented System IME-SIS1 to reflect the

life cycle of the SIS in accordance with BS EN 61508 & BS EN 61511 and to be a working

document throughout the life cycle of the SIS.

SCOPE

Client / Company

-

Immingham Storage Co Ltd

Location / Facility

-

ISCo East Terminal

Plant Unit

-

Tanks 561, 564 & 568

Service

-

No4 East Storage Tank Overfill Protection

SIS Tag No

-

IME-SIS1

SIF’s Tag No’s

-

TK561-SIF1, TK564-SIF1 & TK568-SIF1

SIL

-

2