![Show Menu](styles/mobile-menu.png)
![Page Background](./../common/page-substrates/page0032.jpg)
30
CONSTRUCTION WORLD
JULY
2015
PROJECTS AND CONTRACTS
Kobus Geyer, contract manager for
Gauteng Piling, says 145 piles were
provided by the company for Summit
Place, Phase II: Building E, being constructed by
GD Irons Construction, for Neo Trend Property
Developers. The new Summit Place building
will, on completion be an A+ Grade office park
with about 9 000 m
2
of office space, highly
visible just off the N1 highway on Garsfontein
Road, opposite Menlyn Shopping Centre.
The auger cast in-situ piles provided by
Master Builders Association North member,
Gauteng Piling, were formed by drilling holes
of various sizes and depths into the ground,
placing steel reinforcement into the holes, and
then filling the holes with concrete.
Says Kobus Geyer: "The major piling chal-
lenge for this project was the exceptionally
rocky site. Themany large underground builders
struck during the drilling operations took quite a
heavy toll on our rigs and a high level of main-
tenance had to be kept up throughout the piling
operations," Geyer stated. "Gauteng Piling was
prepared for boulders as we had, a few years,
handled the piling for the Hotel Fire & Ice, which
was built in late 2013 on ground adjacent to the
site where the new office development is now
taking place. But the severity of the boulders and
rocky terrain we encountered this time posed
even greater challenges than two years ago."
The 145 piles provided over an area of about
3 600 m
2
for The Summit were all 11 metres
deep to cope with the rocky strata, and varied
in diameter from 600 mm to 1 650 mm.
The pile bearing capacity ranged from
1 000 kN per m
2
for the smallest diameter pile,
to 13 500 kN per m
2
for the biggest. Bearing
capacity determines the maximum load the soil
can safely carry during piling operations.
Steel reinforcement cages inserted into the
piles ranged from 450 mm to 1,5 m in diameter.
Gauteng Piling – which employed aWilliams
LDHH digger and a SoilMec hydraulic drilling rig
for the piling foundations – subsequently was
awarded a contract for another 34 piles on the
western side of the Summit Place site.
The company has in the past 18 years
completed over 1 500 projects to become
one of the major players in the piling industry
in Gauteng. The company – which provided
the piling foundations for the massive Mall
of Africa last year - has a fleet of 20 auger
drilling machines, two cranes, two bore
rigs, four Grundo hammers, and two lateral
support machines.
ROCKY CHALLENGE AT
GARSFONTEIN SITE
Gauteng Piling recently successfully coped with exceptionally rocky
strata to complete the piling foundations for a new 15-storey office
block in Pretoria.
A photograph showing a typical underground
boulder that made the foundation excava-
tions a formidable task.
An overall view of the start of the Gauteng Piling
operations at Summit Place with concrete being
poured into one of the piling holes.
>
I
Shortly after this project was initiated,
Kwikspace was contracted to construct
two offices at the Neckartal Dam
Project site for Salini Namibia the construction
and engineering and company responsible for
the construction of the dam.
Measuring 1 206 m² in total, the two offices
were set up as site-erected buildings, which
allowed for easy transport of the building
materials and on-site completion according to
the clients’ specifications. In this instance, the
Salini office measures 758 m² and the engineer’s
office 448 m². On completion of these buildings
towards the end of last year, over 60 employees
were provided with office space.
Never afraid of a challenge, Kwikspace
CONTRIBUTING TO NAMIBIA’S DEVELOPMENT
completed the construction of these two
buildings at the top of a plateau, with a valley
reaching 120 metres below, where winds can
reach up to 120 km per hour.
The construction of the Neckartal Dam is of
great significance to the country as it will create
a reservoir capable of holding 857 million cubic
metres of water, based on figures by Salini. When
completed, the dam will bring about economic
growth and prosperity in the country as it will
be used for power production, irrigation and
agricultural development. In addition, the
development thereof has created a number of
job opportunities.
To ensure the smooth running of the devel-
opment process, the speedy completion of infra-
structure such as this office space for the client
and main contractor is an essential factor. For
this reason, Kwikspace’s prefabricated buildings
are highly suitable to the project requirements.
Comments Nick Alexander, director of busi-
ness development for Kwikspace Modular Build-
ings in Africa:“Our involvement at the Neckartal
Damwas a great success. As a company, we are
always pleased to contribute to projects that
facilitate positive developments in a country.”
>
South African company, Kwikspace Modular Buildings (Kwikspace),
recently broke new ground in the rentals market in Namibia
when it delivered its first ever rental units in the country for use
as accommodation by the construction team involved with the
development of the Neckartal Dam.