Background Image
Previous Page  46 / 64 Next Page
Information
Show Menu
Previous Page 46 / 64 Next Page
Page Background

44

CONSTRUCTION WORLD

JULY

2015

PORTS AND HARBOURS

Franki engineer Paul Pearce says

the existing pier is a reinforced

concrete deck supported on

precast concrete piles which retain

a rock groyne beneath the pier. “Due to scour

and failure of the precast piles, approxi-

mately 75 m of the seaward end of the pier

has failed and is to be demolished and recon-

structed,” Pearce says.

The main scope of works includes the demo-

lition of 75 m of the existing piling and deck;

installation of 22 no. 750 mm diameter x

24 m permanently cased piles; construc-

tion of 75 m x 10 m wide new deck and

the installation of 500 no. 4-ton geotextile

scour protection bags within and around

the seaward end of the pier. “The existing

pier has continued to move due to the failed

piles and in order to safely demolish the old

pier and construct the new one, we have

constructed a 110 m temporary jetty adjacent

to the existing structure as a working plat-

form,” Pearce says.

The temporary jetty was completed in

June 2014. Obstructions, including large

boulders and concrete, below the sea bed

have caused difficulties in installing piles

and these had to be broken through using

chisels and grabs resulting in lengthy delays.

Where the existing failed piles obstructed

the proposed new pile positions, the jetty

has had to be redesigned to accommodate

new pile positions. All piles have now been

installed to depth, with one pile having to be

installed at a rake.

Ongoing settlement of the rock within

the groyne and in the sea bed around the pier

are causing the engineers some

concern and additional scour protection

measures are being taken to stabilise the

situation and ensure the groyne serves its

intended function of beach sediment control

– and producing a decent, but safe, wave for

the surfers.

Reconstruction of the deck has started

at the seaward end of the pier with the

existing structure being cut into manageable

pieces and removed to dump. The existing

precast piles are being braced and incorpo-

rated into a new capping beam below the

new structure.

The new deck, which will be approximately

4 m wider than the existing deck, will be

constructed in 11 sections. Custom shut-

tering supported on the new and the existing

piles is being used. The deck design and

the formwork have had to be modified to

accommodate the revised pile positions and

the raked pile.

As with all marine works, the risks associ-

ated with rough sea conditions are ever-

present making the fixing and maintaining

of the deck shuttering challenging. One of

the measures taken to speed up preparation

works to avoid the exposure time is the use

of glass fibre coated polystyrene blocks for

soffits and void filling.

Currently Franki’s Siva Govindasamy, a

veteran Durban pier builder having worked

on Dairy Beach Pier, uShaka Pier, Umhlanga

Pier and the more recent Argyle Stormwater

outlet, and James van Wyk are supervising

the works.

Due to the unforeseen ground condi-

tions and associated delays, the works are

currently behind schedule with contract

completion scheduled for December 2015.

Bay of Plenty

PIER

After a lengthy delay due to an appeal against the award, Franki

Africa (KZN) was appointed by eThekweni Municipality in October

2013 to carry out the reconstruction of the Durban Bay of Plenty Pier

and commenced work in March 2014.

>