CITY OF MORGAN HILL

CAPITAL IMPROVEMENT PROGRAM

2017-2022 Six-Year Capital Improvement Program

PAGE : 43 OF 123

Expenditure Schedule & Category

Streets & Roads: 502000

2016-17

2017-18

2018-19

2019-20

2020-21

2021-22

86220 - Architecture and Design

$30,000

$35,000

$40,000

86360 - Construction

$180,000

$400,000

$450,000

86530 - Project Implementation

$40,000

$45,000

$50,000

PROJECT COST

$250,000

$480,000

$540,000

Funding Source(s)

2016-17

2017-18

2018-19

2019-20

2020-21

2021-22

f309 - Traffic Impact Fund

$25,000

f346 - Public Facilities (NonAB1600)

Fund

$225,000

$480,000

$540,000

FUNDING TOTALS

$250,000

$480,000

$540,000

Estimated Project Schedule

2016-17

2017-18

2018-19

2019-20

2020-21

2021-22

Quarter

1

2

3

4

1

2

3

4

1

2

3

4

1

2

3

4

1

2

3

4

1

2

3

4

Planning

__

__

__

Project Design

_____

_____

_____

Right-of-Way Acquisition &

Permitting

Construction

_____

_____

_____

Project Closeout

__

__

__

Operating Cost Impacts

Maintenance of new traffic signal to be performed by Community Services Maintenance Division at an estimated

additional annual operating cost of $1,500 per signal.