CITY OF MORGAN HILL

CAPITAL IMPROVEMENT PROGRAM

2017-2022 Six-Year Capital Improvement Program

PAGE : 46 OF 123

Project

Pavement Rehabilitation Program

Project No.

519000

Category

Streets & Roads

Department

Public Works

Council Priorities

Enhancing Public Safety

Location

Citywide

Project Description

This ongoing program is intended to address the City's pavement rehabilitation needs. Locations for

maintenance are selected based on recent Pavement Management Program (PMP) data and field observations

from Street Maintenance crews. Projects by Fiscal Year:

o FY16/17: Overlay Monterey Rd (Dunne to East Middle), guardrail installation on Thomas Grade, slurry and crack

seal work in Jackson Meadows neighborhoods.

o FY17/18: Overlay East Dunne Avenue (Hill to Thomas Grade), Overlay Monterey Road (Tilton to Peebles), slurry

and crack seal in Central Park, Morgan Lane, and Kendall Hill neighborhoods.

o FY18/19: Street maintenance locations to be determined following update of the City's Pavement Management

Program in the Spring of 2017.

Project Justification

Extends the surface life of streets, thus reducing repair costs in the future. The 2016 Pavement Management

Program (PMP) update recommends needed rehabilitation of $3.9 million per year to maintain the City's current

pavement condition index (PCI) of 67, though the deferred maintenance backlog will increase from $25.2 million

to $30.7 million. The latest PMP report indicated a need to invest $6.0 million annually to increase the PCI from

67 to 72 and stabilize the backlog at $22.9 million by FY 20-21.