Previous Page  21 / 69 Next Page
Information
Show Menu
Previous Page 21 / 69 Next Page
Page Background

Simon Storage Ltd – Immingham East Terminal

Gasoline Import – Layers of Protection Analysis

P & I Design Ltd

DOCUMENT NO: SI057001_RPT

2 Reed Street, Thornaby, UK, TS17 7AF

ISSUE: G DATE: 29.06.12

Tel: + 44 (0)1642 617444

PAGE 21 OF 34

Fax: + 44 (0)1642 616447

www.pidesign.co.uk

leak tests the hose and restarts the import to the new tank. The operator attends the tank as

before to confirm that the import starts.

At the end of the import, the ship will stop automatically having completed the export of its

cargo. There will be contact between the tank-side, jetty operator and the ship to confirm the

completion of the import. Once the import is complete the ship will stop its pumps and

isolate the ships manifold. The jetty hose will be cleared of product into the import line and

isolated. The hoses will then be disconnected. The jetty line to the hose-pit will then be

pigged clear. There is a maximum amount of 50 m

3

that will be sent to the tank during this

operation.

No tank to tank transfers are routinely carried out. If a tank is to be taken out of service then

any transfer is carried out under management procedures.

ATG Alarms via VTW System

Topping Off Alert (Facility available, set 60 minutes from predicted finish time)

Normal Fill Level Alert (Set at 95% at present)

High Level Alarm (Set at 96% at present)

The normal fill level alert and high alarms are purely audible alarms within the control room

and transmitted through the radio system.

Other alarms

There is an independent high high level switch and shutdown system which closes the

Automated Shutdown valve on the receiving tank inlet. The activation of the switch is

transmitted to a control room annunciator and repeated to the radio system. (Set at 97% at

present)

(For tank 561 = 6931mm, time to overfill after high high level activated: 5.4 minutes)

(For tank 564 = 8662mm, time to overfill after high high level activated: 9.9 minutes)

(For tank 568 = 8662mm, time to overfill after high high level activated: 9.9 minutes)

Power Failure

In the event of a site wide power failure the terminal operator will contact the jetty to stop

transfer.

The VTW, annunciator and radio base station are powered by a UPS. Level monitoring on

tanks will fail. The high high level switches will activate and the shutdown valves will close.