Local Fuel plc – Shoreham Oil Terminal

Safety Instrumented Systems – Policy and Lifecycle Activities

P & I Design Ltd

DOCUMENT NO: LF364003_RPT

2 Reed Street, Thornaby, UK, TS17 7AF

ISSUE: C DATE: 12.06.15

Tel: 00 44 (0)1642 617444

PAGE 18 OF 19

Fax: 00 44 (0)1642 616447

www.pidesign.co.uk

7.5

Modification

Safety lifecycle

Phase

Activity

Required Competencies

Modification

Management of

Change Control

Knows and understands site procedures

for management of change.

Has carried out a risk assessment for

management of change.

Knows how to modify SIS to achieve

required revised functionality and integrity

and implications of the changes.

Has managed and/or developed revised

documentation and procedures associated

with SIS modifications.

Specification, Design,

Implementation

and Testing

of Modification

For any activities included in

Design and Engineering,

Installation Commissioning and Validation

or Operation and Maintenance above,

the same competencies are required for

modifications.

7.6

Decommissioning

Safety lifecycle

Phase

Activity

Required Competencies

Decommissioning

Decommissioning

Knows and understands how to

decommission SIS while ensuring hazards

are managed.

Has experience of decommissioning SIS in a

safe manner.

7.7

Verification

Safety lifecycle

Phase

Activity

Required Competencies

Verification

Checking and approval

of lifecycle

documentation

Knows how to carry out verification reviews.

Has experience of verifying two or more

lifecycle activities.