the fault that is approximately east-west
striking and steeply north dipping.
KICO has a significant amount of
underground infrastructure at the Kipushi
project, including a series of vertical mine
shafts, with associated head frames, to var-
ious depths, as well as underground mine
excavations.
The newest shaft, No 5 (labelled as P5
in the schematic section), is 8 m in diam-
eter and 1 240 m deep. It is expected to be
recommissioned as the main production
shaft. It has a maximum hoisting capacity
of 1,8Mt/a and provides the primary access
to the lower levels of the mine, including
the Big Zinc Zone, through the 1 150 mL
haulage level. Shaft 5 is located approxi-
mately 1,5 km from the main mining area.
A series of crosscuts and ventilation infra-
structure are still in working condition. The
underground infrastructure also includes
a series of pumps to manage the influx of
water into the mine.
The planned mining method is a com-
bination of sublevel open stoping (SLOS),
pillar retreat and cut and fill methods at a
steady-state mining rate of 1,1 Mt/a.
The primary mining method for the
Big Zinc Zone in the PEA is expected to
be SLOS, with cemented rock backfill. It is
anticipated that the crown pillars will be
mined once adjacent stopes are backfilled
using a pillar retreat mining method. The
Big Zinc Zone is expected to be accessed
via the existing decline and without sig-
nificant new development. The main levels
are planned to be at 60-m vertical intervals,
with sublevels at 30-m intervals.
The cut and fill mining method will be
used to extract the copper zone outside
the Big Zinc Zone. In this method, mining
occurs in horizontal slices, with the blasted
copper material removed from the stopes,
then crushed underground and sold at the
mine gate.
The planned process plant in the PEA
is a dense media separation (DMS) plant,
which is expected to include crushing,
screening, heavy-liquid separation (HLS)
and spirals to produce a high-grade zinc
concentrate. DMS is a simple density con-
centration technique that preliminary
testwork has shown yields positive results
for the Kipushi material, which has a suf-
ficient density differential between the
gangue (predominantly dolomite) and
mineralisation (sphalerite). DMS wash-
ability profiles were evaluated in the
laboratory at three feed-crush sizes using
a combination of HLS and shaking tables.
Preliminary test work results on three
crush sizes indicated that the –20-mm
crush size resulted in the highest recov-
ery and concentrate grade. This crush size
achieved an overall recovery of 95,4 % at a
concentrate grade of 55,5 % zinc.
Kipushi, which was placed on care and
maintenance in 1993, flooded in early 2011
due to a lack of pump maintenance over
an extended period. At its peak, water
reached 851 m below the surface level. A
major milestone was reached in December
2013 when Ivanhoe restored access to the
mine’s principal haulage level at 1 150 m
below the surface. Since then, crews have
been upgrading underground infrastruc-
ture to permanently stabilise the water
levels and support the drilling programme.
Recent improvements to Shaft 5 have
included dewatering to expose the main
pump station at the 1 200-m level, instal-
lation of new hoist ropes on the Shaft 5
Maryanne rescue hoist, stripping of the
1 200-m level pump station and refur-
bishment and commissioning of the
friction-reeler gearbox.
Sedgman selected to design and build Boikarabelo plant
Resource Generation Limited (ResGen),
listed on the ASX and JSE, has announced
the conclusion of a Heads of Agreement
and Letter of Intent (LOI) for the design,
procurement and construction of the Coal
Handling and Preparation Plant (CHPP) for
the Boikarabelo coal mine in South Africa’s
Waterberg region.
The agreement with Sedgman Limited,
a member of the CIMIC Group and a
leading Engineering, Procurement and
Construction (EPC) contractor in coal and
minerals, provides for a fixed lump sum
contract for US$141 million subject to
exchange rate fluctuation. The contract
price represents a substantial saving over
the previously announced estimate and
was achieved as a result of the Sedgman
design offering a smaller footprint with
associated capital savings while offering
equal, if not improved, production outputs.
In addition, under the provisions of the
LOI ResGen has indicated an intent to nego-
tiate a three-year CHPP operations contract
with Sedgman effective following the
expiry of a 15-month operations contract
to cover the warranty period post commis-
sioning and to negotiate with Sedgman a
contract for the construction of the ancillary
infrastructure works.
Rob Lowe, Chief Executive Officer of
ResGen, commented: “The conclusion of
the EPC contract with a leading contractor
based on the significantly reduced capital
cost of the project is a major milestone for
the Boikarabelo mine and ResGen, and is a
step closer to securing full funding for its
completion. The board has continued on its
stated path of materially reducing risk and
capital expenditure.”