Previous Page  211 / 482 Next Page
Information
Show Menu
Previous Page 211 / 482 Next Page
Page Background

GAZETTE

A

pril

1989

Summary judgment on foot of

an architect's certificate - a

conflict resolved?

A decision of Costello J. handed down on the 19th January, 1989,

on the issue of Summary Judgment on foot of an Architect's

Interim Certificate, is of considerable importance. At one time, it

was thought that an Architect's Interim Certificate was almost the

equivalent to a Bill of Exchange and had to be honoured on

presentation. An employer could not seek to set off against a claim

on foot of an Architect's Interim Certificate, a proposed counter-

claim in respect of defective workmanship. The situation was

similar to claims in respect of freight in Admiralty Law.

The landmark English decision on or any other contract." It was held

this matter was that of

Dawnays

Limited -v- F. G. Minter Limited

11971] 2 All E.R. 1389. That was

the case where Denning M. R. held

that the provisions of the Contract

which required Interim Certificates

to be paid within 14 days were

inconsistent with the right of set

off. He pointed out that the matters

which could be deducted from an

Interim Certificate were clearly set

out e.g. retention monies, monies

previously paid etc., and did not

include

coun t e r c l a ims

for

unliquidated damages for defective

wo r kmansh ip or delay. That

reasoning was followed in a

number of English cases. However,

in more recent times, that principle

was effectively reversed by two

House of Lords' decisions and one

decision of the Irish High Court.

The principal English case was that

of

Gilbert-Ash (Northern) Limited -

v- Modern Engineering

(Bristol)

Limited

[1973] 3 All E.R. 195. In

that case a clause permitting a

contractor to withhold sums from

a sub-contractor was in the

following terms:- " I f the sub-

contractor fails to comply with any

of the conditions of the sub-

contract, the contractor reserves

the right to suspend or withhold

payment . . . the contractor also

reserves the right to deduct from

any payment certified as due . . .

the amount of any bona fide contra

accounts and/or other claims which

he . . . may have against the sub-

contractor or contractor with this

t hat this en t i t l ed the main

contractor to deduct unliquidated

damages for breach of warranty.

(Clearly, the wording of this clause

is very different to the wording of

the 19777 R.I.A.I. Form of Agree-

ment.) However, three of the Lords

Justices took the opportunity to

disapprove of the earlier decision in

Dawnays

case. They held that a

counterclaim in respect of defective

workmanship could be the subject

matter of a set off against a claim

on foot of an Architect's Interim

Certificate. The second English

case was a case of

Aries Tanker

Corporation

-v- Total Transport

Limited [

1971] 1 All E.R. 398. This

was a shipping case which affirms

the rule of Common Law that a

claim in respect of cargo cannot be

deducted from freight. The House

of Lords stated

obiter

in that case,

that counterclaims in respect of

defective workmanship could be

set off against a claim on foot of an

Architect's Interim Certificate and

again, disapproved of the

Dawnays

decision. On the basis of these

decisions, the editors of Emden's

Building Contract and Practice, 8th

Edition (1980) page 98 conclude:-

"Accordingly, it is submitted that

the Law at present is that set offs

may be raised in actions on Certifi-

cates in the same way as in other

actions for work and materials, and

that the contrary view is not now

sustainable."

Irish case law

There is only one reported Irish

case and that is the case of

P. J.

Hegarty -v- Royal Liver Friendly

Society

[1985] I.R. 524. There had

been an earlier unreported decision

on the topic

John Sisk & Son Ltd.

-v- Lawter Products B.V.

(Finlay P.

15th November, 1976). In the

earlier decision, Finlay P. had

considered a claim for summary

judgment on foot of an Architect's

Certificate for the sum of

£168,537. In that case, Finlay P.

considered a contract which was in

the standard form of the R.I.A.I.

(1966 edition). He reviewed the

relevant clauses and in considering

the issue of whether or not a

counterclaim could be raised by

way of set off against an

Architect's Certificate, stated the

relevant principle of law as follows:-

" I believe the true test to be not

whether the common law right of

set off has, by the terms of the

Building Contract been unequivo-

cally excluded, but rather as to

whether all the relevant terms of

the Building Contract are in any

particular event inconsistent with

the exercise in that event of such

a right of set off." Finlay P.

concluded that the relevant terms

of the 1966 edition were incon-

sistent with the exercise of a right

of set off and granted summary

judgment for the amount claimed.

In the

P. J. Hegarty -v- Royal Liver

Friendly Society

case, Murphy J.

refused to grant judgment in

summary summons proceedings

on foot of an Architect's Certifi-

cate, pending the hearing of a

counterclaim, since he held that the

197