Previous Page  212 / 482 Next Page
Information
Show Menu
Previous Page 212 / 482 Next Page
Page Background

GAZETTE

JULY 1989

decree on the counterclaim could

be set off against the claim on foot

of an Architect's Certificate.

This decision appears to be

diametrically opposed to the

decision of Finlay P. in

Sisk -v-

Lawter.

Murphy J. (who was

considering a contract in the form

of the 1977 edition of the R.I.A.I.

Standard Form) chose not to follow

that case. He accepted that the

principles were correctly set out by

Finlay P. in the passage quoted

above, and said that he would have

been extremely slow to differ from

the conclusion reached by the

President of the High Court were it

not for what he regarded as "an

important distinction" namely, that

the latter half of clause 38 (the

arbitration clause) of the 1977

edition of the R.I.A.I. form provides

that "such reference, e x c ep t . .. on

the question of certificates, shall

not be opened . . ." This it is sub-

mitted, was not an important

distinction at all for t wo reasons.

Firstly, it is submitted that if one

reads the clause in its entirety, the

clause appears to contemplate that

the principal " q u e s t i on

of

certificates"'about which there will

be a dispute or difference is the

withholding of one (the clause

begins . . . " i n case any dispute or

difference shall arise between the

employer and the architect on his

behalf and the c on t r a c t o r . .. as to

the construction of the contract or

as to any matter or thing arising

thereunder or as to the withholding

by the architect of any certificate

. . ."). It is possible to imagine a

dispute arising during the course of

the contract as to the interpretation

of a certificate. Apart from that

however, it is submitted that the

mere use of the words "question of

certificates" in the context of the

arbitration clause does not justify

an inference that the liability to pay

an interim certificate on presen-

tation, is anything other than an

absolute one. Secondly, apart from

one or two minor differences, there

is no distinction between the

wording of the arbitration clause in

the 1966 and 1977 editions of the

R.I.A.I. standard form. Murphy J.

concluded his judgment in the

P. J.

Hegarty

case saying that even if he

had decided it differently, he would

nevertheless have granted a stay of

execution on the judgment on foot

of the certificate to enable the

counterclaim to be prosecuted. As

can be seen, the law in relation to

this area was left in a most unsatis-

factory situation as a result of the

conflict between these two Irish

decisions.

Rohan Construction Ltd. -v-

Antigen

This is the importance of the recent

decision of Costello J. The claim by

Rohan Construction Limited was

for summary judgment on foot of

an Architect's Interim Certificate in

the sum of £191,116 and interest

accruing thereon. The Defendants

brought a Motion seeking to stay

the proceedings pending arbitration

of a claim by them for a sum of

approximately £400,000 damages

in respect of alleged defective

workmanship and materials. It had

been agreed between the parties

that this proposed claim against

the contractors should be referred

to arbitration and final decision of

an agreed arbitrator. However, the

Plaintiffs disputed the Defendants

entitlement to stay their claim on

foot of the Architect's Interim

Certificate pending the outcome of

the arbitration or to seek ultimately

to set off the Defendants' award in

the arbitration (if any) against the

claim on foot of the certificate.

Costello J. held that just like the

1966 ed i t i on of the R.I.A.I.

Standard Form, the relevant terms

of the 1977 ed i t i on were

inconsistent with the exercise of a

right of set off against a claim on

foot of an Architect's Certificate.

He expressly followed the decision

of Finlay P. in

Sisk -v- Lawter

and

declined to follow the decision of

Murphy J. in

P. J. Hegarty -v- Royal

Liver.

Accordingly, he refused to

stay the claim for summa ry

judgment pending arbitration.

However, the Defendants also

raised the additional point of a stay

of

execu t i on

pending

the

determination of the arbitration.

This application was made under

Order 42 Rule 17 of the Rules of the

Superior Courts. Referring to the

unreported decision of Barrington

J. in

Agra Trading -v- The Minister

for Agriculture

(19th May, 1988)

Costello J. refused a stay of

execution on the basis that the

agreement of the parties as

reflected by the terms of the 1977

edition of the R.I.A.I. Standard Form

was that there should be no set off

and accordingly, to grant a stay of

execution would be inconsistent

with the intention of the parties and

in normal circumstances it would

not be proper to grant a stay of

execution. He pointed out that the

Court still had discretion in cases

such as this to grant a stay of

execution but there must be

"special reasons" for overriding the

intention of the parties and in this

case, not only were there no special

reasons for doing so, but there

were reasons of some substance

against granting a stay namely, that

a considerable portion of the

A r c h i t e c t 's

Ce r t i f i ca te

was

earmarked for sub-contractors and

the principal contractors were

effectively trustees of this money

and the sub-contractors ought not

to be prejudiced in this way simply

because the employers raise a

counterclaim against the principal

contractors.

In the light of the decision of

Costello J. in

Rohan Construction

-v- Antigen,

it seems clear that

P. J.

Hegarty -v- Royal Liver Friendly

Society

no longer represents good

law in this j u r i sd i c t i on and

Architect's Interim Certificates

issued under the 1977 edition of

the R.I.A.I. Standard Form cannot

be subject to a set off in respect of

claims for unliquidated damages

nor, in the absence of special

circumstances, can judgments for

sums owing on foot of Architect's

Interim Certificates be subject to a

stay of execution so as to enable

employers to prosecute claims in

respect of defective workmanship

or materials.

James Nash

F.S.S. DÍ

P

.

Forensic Document Examiner

and

Handwriting Consultant

38, Monastery Rise,

Clondalkin, Dublin 22.

Telephone: (01) 571323

198