Background Image
Previous Page  182 / 252 Next Page
Information
Show Menu
Previous Page 182 / 252 Next Page
Page Background

NEGOTIATION

170

CHAPTER 7

• The price had to be free of escalation and Company A required retention of

at least 10%.

• Assuming requirements were met, Company A was prepared to make an

upfront payment, as cash flow was not the problem on this project. However,

this was limited to a maximum of 20% of the total contract price.

A7.1.3.1 Strategy

Under the above circumstances, it would have been understandable if Company

A had attempted to force concession on all its requirements, particularly in light

of the intelligence on Supplier X’s financial state. A win-lose approach would

probably have delivered a low price and all the other desired warranties and

retentions.

The win-lose approach would, however, have jeopardised the relationship to

the extent that Supplier X would probably not have devoted its best resources

to the project, and would possibly even have under-quoted but loaded sundry

costs during project delivery. Furthermore, the win-lose would have guaranteed

that Supplier X would never be so compliant on future projects when its order

book was fuller.

Company A chose a win-win strategy for the negotiation. The full wisdom of

this was, however, only revealed during the negotiation itself, as Supplier X

gradually disclosed (in the spirit of co-operation) numerous hidden facts around

its standpoint.

A7.1.4 SUPPLIER X’s INITIAL STANDPOINT

The Supplier X team consisted of the managing director, the marketing director

and the technical director. The supplier needed the business: its order book was

thin and the company was experiencing severe cash flow problems.

The supplier was aware that CompanyAhad experienced problems on the R200

million project. Supplier X, having completed similar projects for Company A

in the past, was expecting hard-line negotiations and a win-lose strategy from

Company A. The major issues for the supplier were:

• The supplier had added a 15% handling commission to sub-contractors’

quotes for much of the detailing and finishing work on the project.

• The delivery period was flexible between four to six months but this was

dependent upon favourable payment terms to alleviate cash flow issues.

• Price escalation was dependent on payment and final retention terms in the

agreement. It was suspected Company A would require a 5% retention, but

would prefer 10%.

• Ideally, it wanted an upfront payment of at least 25% of the total contract

price. Payment for all materials no later than seven days after delivery on

site was essential.

• It understood the value of the named construction manager to the buyer and