MR Linac at ICR / RMH: Timeline
56
Planning permission
Ground breaking
Constructio
n completed
17/12/2014
1/03/2015
03/2016
07/05/2016
Gantry
delivery
04/06/201
Magnet
delivery
RF Cage
install
6
11/07/201
6
12/09/201
6
Setting to work